Hwy 12 Alignment News

Final Environmental Impact Statement for the Nebraska Highway 12 Niobrara East and West Project available for public review
12/12/2024
The Final Environmental Impact Statement, or Final EIS, for the Nebraska Highway 12 Niobrara, or N-12, East and West Project is now available for public review...
USACE preparing Highway 12 Environmental Impact Statement
3/6/2019
The U.S. Army Corps of Engineers – Omaha District is beginning work on a supplemental draft environmental impact statement for the Highway 12 road project in Knox County, Nebraska. ...
Nebraska Highway 12 EIS permit application withdrawn
11/24/2015
Following the November 9 public hearing hosted by the U.S. Army Corps Of Engineers, Omaha District, the Nebraska Department of Roads (NDOR) has withdrawn their permit application for the Nebraska...
Public Open House and Public Hearing set for NE HWY12 – Niobrara Project
10/16/2015
The U.S. Army Corps of Engineers, Omaha District will host an open house and public hearing to provide information and receive public comments on the Draft Environmental Impact Statement and Section...
Draft EIS for NDOR proposed Nebraska Highway 12 project released
10/9/2015
The Draft Environmental Impact Statement for the Nebraska Department of Roads’ proposed Nebraska Highway12 project is now available for public review.The project, coordinated by the Nebraska...
Nebraska Highway 12 – Niobrara East & West Project Update
2/4/2011
This spring, the U.S. Army Corps of Engineers (Corps) will make a preliminary Draft Environmental Impact Statement (EIS) available to the Nebraska Department of Roads (NDOR) and the Nebraska Highway...

Environmental Impact Statement - Highway 12

Nebraska Highway 12 roadway east and west of the Village of Niobrara, Knox County

Summary:  NDOT proposes to construct improvements on two segments of Nebraska Highway 12 near Niobrara, which will be located mostly atop and/or immediately adjacent to the existing roadway. One of the segments, Niobrara West, is approximately 6.2 miles long and extends from just east of Verdel, Nebraska east to two (2) miles west of the N-12 Niobrara River Bridge. The other segment, Niobrara East, is approximately six (6) miles long and extends from just east of Spruce Avenue in Niobrara east, extending into the Santee Sioux Reservation, to approximately one (1) mile east of Spur N-54D. The proposed project raises the existing Nebraska Highway N-12 (N-12) roadway on a parallel alignment for both the west and east segments to a minimum elevation approximately three (3) feet above the projected water surface elevation of the Missouri River during a 1-percent annual exceedance probability (AEP) flood event. This is approximately 4 to 9 feet higher than the existing N-12 profile. In addition, the roadway would be widened to meet current NDOT safety criteria, including 12-foot driving lanes, 8-foot shoulders, 30-foot lateral obstacle clearance, and sloping embankments. Curvature and ingress and egress considerations for county roads and private access would be modified to satisfy current NDOT design standards.  The purpose of the proposed project is to rehabilitate the existing roadway to maximize utilization of existing highway infrastructure, improve safety and reliability, and bring the roadway up to current NDOT design standards for a major arterial highway between Verdel and the Santee Spur (S-54D).

USACE, in response to the Nebraska Department of Transportation’s (NDOT) Project Proposal, in coordination with the cooperating agencies, as part of its Section 408 (Section 14 of the Rivers and Harbors Act of 1899) permission decision and Section 404 (Clean Water Act) permit authorization review processes, and in compliance with the National Environmental Protection Act (NEPA), has developed a Final Environmental Impact Statement (FEIS).

EIS Milestones Completed
Publish Notice of Intent to Prepare EIS (Federal Register)  July 25, 2008
Public Notice of Intent to Prepare EIS (District Public Notice) July 25, 2008
Public Scoping August 2008
Public Meeting July 2009
Publish Notice of Available Draft EIS (Federal Register) October 9, 2015
Press Release of Available Draft EIS October 9, 2015
Public Open House and Hearing November 9, 2015
Public Comments Due November 23, 2015
Permit Application Withdrawn; EIS Status Pending November 20, 2015
Press Release EIS Process Resumes March 20, 2015
Public Notice of Intent to Prepare Supplemental Draft EIS (Federal Register) May 3, 2019
Public Notice of Intent to Prepare Supplemental Draft EIS (District Public Notice) May 3, 2019
Press Release Notice of Intent to Prepare Supplemental Draft EIS and Request for Public Comment  May 2, 2019
Public Scoping May 3 - 24, 2019
Public Notice of Availability Supplemental Draft EIS (Federal Register) January 3, 2020
Public Notice of Availability Supplemental Draft EIS (District Public Notice) January 3, 2020
Press Release Notice of Availability Supplemental Draft EIS January 3, 2020
Public Comments Due February 17, 2020
Public Notice of Availability Final EIS (Federal Register) December 13, 2024
Public Notice of Availability Final EIS (District Public Notice) December 13, 2024
Press Release Public Notice of Availability Final EIS (Federal Register) December 12, 2024
Public Comments on Final EIS Due January 27, 2025
Record of Decision  

 

Highway 12 Final EIS

Collapse All Expand All

Any questions and/or to submit comments in writing contact:  

ATTN: Highway 12 EIS Regulatory Project Manager
U.S. Army Corps of Engineers, Omaha District
Nebraska Regulatory Field Office
8901 South 154th Street
Omaha, Nebraska 68138 Email: ne404reg@usace.army.mil

Federal Register Notice:  https://www.federalregister.gov/d/2024-29368/p-12

USACE Public Notice:  https://www.nwo.usace.army.mil/Missions/Civil-Works/Planning/Project-Reports/Article/3999257/usace-seeks-comment-for-final-environmental-impact-statement-for-the-nebraska-h/      

Highway 12 Draft Supplemental EIS

Collapse All Expand All
Expand List item 36707Collapse List item 36707  Draft Supplemental EIS Release Date: January 3, 2020
Permit Applicant: Nebraska Department of Transportation (NDOT) 
 

Draft Supplemental EIS Prepared by: U.S. Army Corps of Engineers, Omaha District Regulatory Branch (the Corps' Regulatory Branch is neither a proponent nor opponent of the proposed project). A list of libraries and offices where a paper copy of the Draft Supplemental EIS is available in the Public Notice. Comments Due: February 17, 2020 Submit comments in writing to: 

Any questions please contact:  

ATTN: Highway 12 EIS Regulatory Project Manager
U.S. Army Corps of Engineers, Omaha District
Nebraska Regulatory Field Office
8901 South 154th Street
Omaha, Nebraska 68138 Email: ne404reg@usace.army.mil

Expand List item 36710Collapse List item 36710  Documents  

Highway 12 Draft EIS

Collapse All Expand All
Expand List item 36714Collapse List item 36714  Highway 12 Draft EIS

Draft EIS Release Date: October 9, 2015

Permit Applicant: Nebraska Department of Roads (NDOR)

Draft EIS Prepared by: U.S. Army Corps of Engineers, Omaha District Regulatory Branch (the Corps Regulatory Branch is neither a proponent nor opponent of the proposed project).

A list of libraries and offices where a paper copy of the Draft EIS is available in the Public Notice.

Comments Due: November 23, 2015

ATTN: Highway 12 EIS Regulatory Project Manager
U.S. Army Corps of Engineers, Omaha District
Nebraska Regulatory Field Office
8901 South 154th Street
Omaha, Nebraska 68138 Email: ne404reg@usace.army.mil

Tip: Files that are larger than 20 MB will not open automatically. After clicking the link to the section you wish to open, clicking the blue "download" button in the upper right hand corner of the page will improve download efficiency.

Collapse All Expand All

 

[2:17 PM] Fuerst, Lee A CIV USARMY CENWO (USA)

Tip: Files that are larger than 20 MB will not open automatically. After clicking the link to the section you wish to open, clicking the blue "download" button in the upper right hand corner of the page will improve download efficiency.

 November 9, 2015 - N-12 Draft EIS - Open House and Public Hearing

Displays

Transcript

 Draft EIS - Highway 12 Project

The entire report is available in three downloadable files. Click the links to begin downloading. The files are large and may take some time to download.

 Executive Summary

 Volume 1

 Volume II

 Background/Project History:

Part of the EIS process is to screen alternatives. NDOR provides USACE with proposed roadway alternatives that have to meet standard State and local roadways design criteria that specify an area from the driving lane free of obstacles, including above bodies of water. N-12 shall have approximately 7.5 feet of clearance above the 100-year flood elevation, and N-14 shall have approximately 7 feet of clearance above the 100-year flood elevation. 

Flooding in 2011 provided new details and in spring 2013, USACE developed a new floodplain model for a study requested by the Niobrara Public School District. This new model included information from the 2011 flood. USACE then compared the floodplain elevations developed under the new model to the Parallel Alignment (Alternative A2) as it was currently designed. USACE found that this alignment alternative no longer met 100-year flood design criteria, and may also impact other road alternatives. 

With this new information, NDOR chose to redesign the floodplain alternatives to raise the roadway elevations based on the new floodplain modeling. Additionally, NDOR reevaluated its design engineering for the Bluffs Alignment (Alternative B1), redesigning the alignment to reduce the potential for slides and road failures due to the presence of Pierre shale. 

Alternatives Carried Forward figures are available in the HQ USACE Digital Library. The redesign changes the cost of each alternative and wetlands impacts. Because USACE uses cost as a determining factor to practicable alternatives, a new review of alternatives and their costs is needed. USACE also reviews and presents in the EIS each revision for impacts on wetlands and other resources.

2008

2009

2013