  • Releases from Fort Peck Dam to decline during maintenance work

    Releases from Fort Peck Dam will be reduced from 11,000 cubic feet per second to 8,500 cfs on July 28 and then increase slightly to 9,000 cfs on July 29. A Power Plant maintenance project originally scheduled for June was rescheduled for late July. The project will require outages on Units 1, 2, and 3 to support testing on Unit 2.
  • Garrison Dam releases increased

    In order to meet the 44,000 cfs release, the Garrison Project initiated releases of 3,000 cfs through its regulating tunnels. This release supplements the 41,000 cfs release through the power plant for a combined release of 44,000 cfs.