03 February 2021 - Additional damage locations were identified during the site visit for the levee repair contract. The team is working to complete the design for these additional damage locations, but the initial survey work for the design was delayed due to COVID. The design is expected to be complete in the next several weeks..
08 September 2020 - The construction contract advertisement was cancelled due to additional damage locations being identified. The team is currently incorporating these additional locations into the contract and once complete, will re-advertise.
16 July 2020 - The construction contract advertisement was cancelled due to additional damage locations being identified. The team is currently incorporating these additional locations into the contract and once complete, will re-advertise.
10 June 2020 - The levee repair project was advertised on 02 June 2020 and the bid opening is scheduled for 18 June 2020.
08 May 2020 - The levee repair project is ready to be advertised for construction, pending finalization of project documentation by the levee sponsor.
23 April 2020 - The levee repair project is ready to be advertised for construction, pending finalization of project documentation by the levee sponsor.
10 April 2020 - The levee repair project is ready to be advertised for construction, pending finalization of project documentation by the levee sponsor.
16 March 2020 - The team is finalizing the levee repair design and anticipates advertising this construction contract within the next few weeks.
04 March 2020 - The team is finalizing the levee repair design and anticipates advertising this construction contract within the next few weeks.
13 February 2020 - The team is finalizing the levee repair design and anticipates advertising this construction contract within the next few weeks.
31 January 2020 - The team is finalizing the levee repair design and anticipates awarding the construction contract in early calendar year 2020.
10 January 2020 - The team is finalizing the levee repair design and anticipates awarding the construction contract in early calendar year 2020.
18 December 2019 - The team is finalizing the levee repair design and anticipates awarding the construction contract in early calendar year 2020.
06 December 2019 - The team is finalizing the levee repair design and anticipates awarding the construction contract in early calendar year 2020.
22 November 2019 - The team is finalizing the levee repair design and anticipates awarding the construction contract in early calendar year 2020.
08 November 2019 - The team continues engineering and design work on repairing the Sioux Falls levee system and is anticipating awarding the construction contract in early calendar year 2020.
24 October 2019 - The team continues engineering and design work on repairing the Sioux Falls levee system and is anticipating awarding the construction contract in early calendar year 2020.
13 October 2019 - The team continues engineering and design work on repairing the Sioux Falls levee system.
27 September 2019 – Engineering and design funds have been received. The team is now developing a schedule for the levee repair design work.
13 September 2019 – The team is awaiting receipt of funding from USACE HQ to begin designing the Sioux Falls levee system repairs.
06 September 2019 – The team has requested and is awaiting Engineering & Design funds to begin designing the levee repairs. An in-house design team is being identified within the Omaha District to complete this design effort.
29 August 2019 – Eligibility of levee repairs under PL 84-99 has been approved. The team is now awaiting Engineering & Design funds to begin designing the repairs.
23 August 2019 – The damage assessment and economic analysis report will be sent to the Northwest Division within the next week for the final determination on eligibility of repairs.
05 August 2019 – The team continues to finalize the damage assessment and economic analysis report to make a final determination on eligibility for PL 84-99 Rehabilitation Assistance.
01 August 2019 – An initial site damage assessment been completed. The team is finalizing the damage assessment and economic analysis report to make a final determination on eligibility for PL 84-99 Rehabilitation Assistance.