08 September 2020 - The construction contract advertisement was cancelled due to additional damage locations being identified. The team is currently incorporating these additional locations into the contract and once complete, will re-advertise.
16 July 2020 - The construction contract advertisement was cancelled due to additional damage locations being identified. The team is currently incorporating these additional locations into the contract and once complete, will re-advertise.
10 June 2020 - The levee repair project was advertised on 02 June 2020 and the bid opening is scheduled for 18 June 2020.
08 May 2020 - The levee repair project is ready to be advertised for construction, pending finalization of project documentation by the levee sponsor.
23 April 2020 - The levee repair project is ready to be advertised for construction, pending finalization of project documentation by the levee sponsor.
10 April 2020 - The levee repair project is ready to be advertised for construction, pending finalization of project documentation by the levee sponsor.
16 March 2020 - The team is finalizing the levee repair design and anticipates advertising this construction contract within the next few weeks.
04 March 2020 - The team is finalizing the levee repair design and anticipates advertising this construction contract within the next few weeks.
13 February 2020 - The team is finalizing the levee repair design and anticipates advertising this construction contract within the next few weeks.
31 January 2020 - The team is finalizing the levee repair design and anticipates awarding the construction contract in early calendar year 2020.
10 January 2020 - The team is finalizing the levee repair design and anticipates awarding the construction contract in early calendar year 2020.
18 December 2019 - The team is finalizing the levee repair design and anticipates awarding the construction contract in early calendar year 2020.
06 December 2019 - The team is finalizing the levee repair design and anticipates awarding the construction contract in early calendar year 2020.
22 November 2019 - The team is finalizing the levee repair design and anticipates awarding the construction contract in early calendar year 2020.
08 November 2019 - The team continues engineering and design work on repairing the Sioux Falls levee system and is anticipating awarding the construction contract in early calendar year 2020.
24 October 2019 - The team continues engineering and design work on repairing the Sioux Falls levee system and is anticipating awarding the construction contract in early calendar year 2020.
13 October 2019 - The team continues engineering and design work on repairing the Sioux Falls levee system.
27 September 2019 – Engineering and design funds have been received. The team is now developing a schedule for the levee repair design work.
13 September 2019 – The team is awaiting receipt of funding from USACE HQ to begin designing the Sioux Falls levee system repairs.
06 September 2019 – The team has requested and is awaiting Engineering & Design funds to begin designing the levee repairs. An in-house design team is being identified within the Omaha District to complete this design effort.
29 August 2019 – Eligibility of levee repairs under PL 84-99 has been approved. The team is now awaiting Engineering & Design funds to begin designing the repairs.
23 August 2019 – The damage assessment and economic analysis report will be sent to the Northwest Division within the next week for the final determination on eligibility of repairs.
05 August 2019 – The team continues to finalize the damage assessment and economic analysis report to make a final determination on eligibility for PL 84-99 Rehabilitation Assistance.
01 August 2019 – An initial site damage assessment been completed. The team is finalizing the damage assessment and economic analysis report to make a final determination on eligibility for PL 84-99 Rehabilitation Assistance.