Background: The L575-594 Benton-Washington – Pleasant Valley - Waubonsie Levee System experienced significant damage during the 2019 Flood Event.  This led to five (5) breaches, along with substantial other damages, occurring throughout the Levee System.

Current Action: Two priority breaches impacting the I-29 corridor have been identified for initial repairs.  The construction contract for the first of these two breach repairs was awarded on 20 May 2019.  These initial repairs are directed at stopping the flow from the Missouri River into the area behind the levee system and providing an incremental level of flood risk management.  Follow-on actions to repair the second priority breach as well as to further repair the levee system and provide additional flood risk management are being coordinated within the PL 84-99 program. 

 

Initial Breach Repair # 1 – 1.25 mi. SW of Bartlett, IA                                                                                                   

Contractor

Diamond Group Engineering of Santa Ana, CA

 

Contract Amount

$250,000

 

Contract Award

May 20, 2019

 

  Construction Start

May 21,2019

 

Estimated
Completion

Update pending due to recent high-water.

 

 

11

 

 

 

 

 

 

 

Next Steps:

  1. Provide an interim level of flood risk management at the first breach repair location.
  2. Provide an interim level of flood risk management at the second priority breach location.
  3. Conduct physical damage assessment when water levels recede and the levees are accessible
  4. Design and construct levee rehabilitation to authorized level of flood risk management.

L594 Imagery

Photo documents levee L594 breach near Fremont, IA Mar. 14, 2019. (Photo by USACE, Omaha District).
Photo documents levee L594 breach near Fremont, IA Mar. 14, 2019. (Photo by USACE, Omaha District).

Text/HTML

NOAA Water Gauge Levels

Status Updates:

June 2019 – The contractor resumed work on the breach 1-1/4 miles SW of Bartlett, IA on 5 June following the late May high water event. Current plan is to repair damaged levee crest ruts and initially close breach within the next week.

Video Gallery

Embed
Share
Aerial view of Levee L594 Apr. 15, 2019
U.S. Army Corps of Engineers, Omaha District
April 15, 2019 | 9:13
Aerial view of Levee L594 Apr. 15, 2019, following March 2019 runoff event. (Video by Mike Glasch)
More