US Army Corps of Engineers
Omaha District

L536 Levee Restoration Information

Background: The L-536-550 Turkey Creek Left Bank, Rock Creek Left Bank, Missouri River Left Bank, and Mill Creek Right Bank Levee System experienced significant damage during the 2019 Flood Event.  This led to five (5) breaches, along with substantial other damages, occurring throughout the Levee System.

Current Action: Design funding has been received to begin work on the levee repair project. The purpose of this rehabilitation project is to repair the levee system to the authorized level of flood risk management.

Next Steps:

  1. Complete the Engineering and Design process.
  2. Advertise and award the levee repair construction contract.
  3. Repair the system to its authorized level of flood risk management

 

 

 

Status Update:

06 September 2019 – The USACE team continues to work with the levee sponsor to determine the best path forward for repairing the damages levee system.  The schedule for the design and construction of these repairs is still being refined during these ongoing discussions.

29 August 2019 – The USACE team is still coordinating with the Levee Sponsor to determine the overall scope of the project.

13 August 2019 – The USACE team is still coordinating with the Levee Sponsor to determine the overall scope of the project.

31 July 2019 – The USACE team is still coordinating with the Levee Sponsor to determine the overall repair project.

22 July 2019 – The USACE team is still coordinating with the Levee Sponsor to determine the overall repair project.

08 July 2019 – An initial site damage assessment and economic analysis has been completed.  From this initial assessment the USACE team has determined that there are damages to the levee system that are eligible for PL 84-99 Rehabilitation Assistance. The USACE team is coordinating with the Levee Sponsor on the design of the overall levee repair project.

10 June 2019 – An initial site damage assessment been completed.  The team is finalizing the damage assessment and economic analysis report to make a final determination on eligibility for PL 84-99 Rehabilitation Assistance.

NOAA River Level Observations & Forecasts

NOAA Water Gauge Levels

L536 Levee Imagery

Photo documents an aerial view of levee L536 near Atchinson County, Missouri Mar. 19, 2019 after the 2019 runoff event occuring same month. (Photo by USACE, Omaha District)

Video Gallery

Embed
Share
Aerial view of Levee L536 Apr. 15, 2019
U.S. Army Corps of Engineers, Omaha District
April 15, 2019 | 1:49
Aerial view of Levee L536 Apr. 15, 2019 following March 2019 runoff event. (Video by Mike Glasch)
More