US Army Corps of Engineers
Omaha District

Hamburg - Main Ditch 6 Levee Restoration Information

Background: The Hamburg – Main Ditch 6 Left Bank Levee System was damaged during the 2019 Flood Event, leading to the Project Sponsor submitting a Public Law (PL) 84-99 Rehabilitation Assistance request to the US Army Corps of Engineers – Omaha District.

Current Action: Complete the levee repair construction contract.

Restoration Activities:

 

Full Repair Contract 

Contractor

Klutina River Constructors from Irvine, CA

Contract Amount

$3.7M

Contract Award

September 21, 2019

  Construction Start

September 21, 2019

Estimated Completion

January 7, 2020

 

 

 

 

 

 

 

 

Next Step: Repair the system to its authorized level of flood risk management.

Status Updates:

13 October 2019 - The Levee Sponsor (City of Hamburg) and USACE team agreed to delay repairs on the Hamburg-Ditch 6 levee system until next year.  This decision was made to because the team felt that it was best to keep the emergency repairs made to the Ditch 6 levee system in place during this period of elevated flood risk.

27 September 2019 – The levee repair contract was awarded to Klutina River Constructors of Irvine, CA on 21 September 2019 in the amount of $3,777,863 with a period of performance of 120 calendar days.

13 September 2019 – It is anticipated that the Hamburg – Ditch 6 Levee Repair project will be awarded by the end of the month. The Corps team has been coordinating closely with the stakeholder to ensure the construction process will align with local and state efforts to provide a satisfactory level of flood risk management provided by the Hamburg - Ditch 6 Levee System and to ensure repair work will integrate with any future efforts.

04 September 2019 – The team is finalizing the design and construction contract documents, and the official request for proposals is expected to be sent out by the end of this week. This schedule will allow for the construction contract to be awarded by mid-to-late September. 

The Corps team has been coordinating closely with the stakeholders to ensure the construction process will align with local and state efforts to provide a satisfactory level of flood risk management provided by the Hamburg - Ditch 6 Levee System and to ensure repair work will integrate with any future efforts.

29 August 2019 – Final design and construction contract documents, along with official request for proposals, will be released by the end of this week with award of construction contract anticipated in mid-to-late September.  The Corps team has been coordinating closely with the stakeholder to ensure the construction process will align with local and state efforts to provide a satisfactory level of flood risk management provided by the Hamburg - Ditch 6 Levee System and to ensure repair work will integrate with any future efforts.

01 August 2019 – An initial site damage assessment and economic analysis has been completed.  From this initial assessment the USACE team has determined that there are damages to the levee system that are eligible for PL 84-99 Rehabilitation Assistance. Engineering and Design (E&D) work is being initiated for rehabilitating the Hamburg – Ditch 6 levee system. 

NOAA River Level Observations & Forecasts

NOAA Water Gauge Levels

Hamburg Levee Imagery

Flooding at Hamburg – Ditch 6 covered a section of 310th St and the Burlington Northern Santa Fe Rail Line. Photo taken on Mar. 17, 2019.
Flooding at Hamburg – Ditch 6 covered a section Burlington Northern Santa Fe Rail Line. Photo taken Mar. 17, 2019.
Aerial photo of Hamburg – Ditch 6 shows scope of damage from the flooding. Photo taken on Mar. 17, 2019.

Video Gallery