Out with the old, in with the new: Bulkhead gates at Gavins Point Dam replaced for the first time

USACE OMAHA DISTRICT
Published Nov. 18, 2024
A photo of work being done to replace gates at the Gavins Point Project

Contractors from Barnhart Crane and Rigging Co. use a mobile crane to lift a 38,000-pound draft tube bulkhead gate from the tailrace side of the Gavins Point Dam powerhouse October 22, 2024. The gate is original to the dam constructed in 1957 and was replaced in accordance with lifecycle specifications. (U.S. Army Corps of Engineers photo by Delanie Stafford)

A photo of work being done to replace gates at the Gavins Point Project

Scott Swanson, U.S. Army Corps of Engineers, Omaha District contracting officer representative for the Gavins Point Project, provides guidance and quality assurance during the replacement of powerhouse draft tube bulkhead gates October 22, 2024. (U.S. Army Corps of Engineers photo by Delanie Stafford)

A photo of work being done to replace gates at the Gavins Point Project

A contractor from Transco Industries Inc. modifies a metal strap from a draft tube bulkhead gate at the Gavins Point Dam powerhouse October 22, 2024. The new gate replaced an original gate from 1957 in accordance with lifecycle specifications. (U.S. Army Corps of Engineers photo by Delanie Stafford)

A photo of work being done to replace gates at the Gavins Point Project

Contractors from Transco Industries Inc. and Barnhart Crane and Rigging Co. disconnect slings from a 38,000-pound draft tube bulkhead gate that was removed from the tailrace side of the Gavins Point Dam powerhouse October 22, 2024. The gate is original to the dam constructed in 1957 and was replaced in accordance with lifecycle specifications. (U.S. Army Corps of Engineers photo by Delanie Stafford)

A photo of work being done to replace gates at the Gavins Point Project

Contractors from Transco Industries Inc. and Barnhart Crane and Rigging Co. lower a 38,000-pound draft tube bulkhead gate into a guide on the tailrace of the Gavins Point Dam powerhouse October 22, 2024. The new gate replaced an original gate from 1957 in accordance with lifecycle specifications. (U.S. Army Corps of Engineers photo by Delanie Stafford)

A photo of work being done to replace gates at the Gavins Point Project

Contractors from Transco Industries Inc. and Barnhart Crane and Rigging Co. connect slings to a 38,000-pound draft tube bulk head gate at the Gavins Point Dam powerhouse October 22, 2024. The new gates replaced the dam’s original gates from 1957 in accordance with lifecycle specifications. (U.S. Army Corps of Engineers photo by Delanie Stafford)

A photo of work being done to replace gates at the Gavins Point Project

Contractors from Transco Industries Inc. and Barnhart Crane and Rigging Co. lower a 38,000-pound draft tube bulkhead gate into a guide on the tailrace of the Gavins Point Dam powerhouse October 22, 2024. The new gate replaced an original gate from 1957 in accordance with lifecycle specifications. (U.S. Army Corps of Engineers photo by Delanie Stafford)

A photo of work being done to replace gates at the Gavins Point Project

Contractors from Barnhart Crane and Rigging Co. use a mobile crane to lift a 38,000-pound draft tube bulkhead gate from the tailrace side of the Gavins Point Dam powerhouse October 22, 2024. The gate is original to the dam constructed in 1957 and was replaced in accordance with lifecycle specifications. (U.S. Army Corps of Engineers photo by Delanie Stafford)

YANKTON, S.D. – The Gavins Point Dam, operated by the U.S. Army Corps of Engineers, Omaha District, reached a milestone earlier this fall when six draft tube bulkhead gates at the hydroelectric powerhouse were replaced for the first time ever.

The gates date back to 1957 when construction of the dam was completed. They were refurbished once in the 1980s but have not been updated since. Each one is essential to maintaining the hydropower units.

“They’ve reached the end of their lifecycle, so it was time to replace,” said Martin Goding, Gavins Point powerhouse superintendent. “When we go into annual maintenance, they drop these gates, and there are men behind these gates, so it keeps the water out so we can actually do the maintenance on the inside of the unit.”

The gates are situated on the tailrace of the three hydropower generators where water from the Missouri River is channeled once it exits the unit.

The multi-day removal and installation project required patience and some heavy lifting. Each gate weighs 38,000 pounds and had to be moved one at a time by a gantry crane to the closest position within reach of a mobile crane before being lifted out by contracted crane and rigging professionals. Once removed, installation of the new gates was completed in the same manner.

With installation and leakage testing complete, Gavins Point Project mechanics and electricians have now begun annual maintenance on the three hydropower units scheduled for completion in April 2025.

The new gates will ensure maintenance of the hydropower units can continue for at least the next 50 years.

“If the old gates had failed, we would not be able to do the annual maintenance on the units,” Goding said. “Then we’re looking at potential failure of a component that we needed to do repairs to.”

The project cost $4.1 million and took 5 years to complete from design to finish.

Gavins Point Dam was built as part of the Flood Control Act of 1944. When not operating to reduce flood risk, it provides hydropower generation supporting 68,000 homes annually as well as water supply, water quality, irrigation, fish and wildlife conservation, navigation and recreational benefits.


News from around USACE

Liz Suarez earns prestigious award for disaster recovery efforts
6/11/2025
Internal Review Office Chief, Liz Suarez, of the U.S. Army Corps of Engineers, Savannah District, was recently selected as the George A. Sullivan Award recipient due to her efforts during hurricane...
Mapping the Future: How wetland mitigation banking balances conservation and progress
6/11/2025
Deep in the heart of the Brosnan Forest located in Dorchester County, towering longleaf pines stretch across the vast 14,400-acre ecological preserve. The air thickens with the scent of pine needles...
Four ERDC researchers earn DoD SMART awards
6/11/2025
Four researchers in two laboratories at ERDC were recently awarded the 2024 Department of Defense (DoD) Science, Mathematics, and Research for Transformation (SMART) Scholar & Mentor of the Year...
New York District Honors 250 Years of Army Engineering Excellence
6/11/2025
NEW YORK – As the U.S. Army Corps of Engineers marks its 250th Anniversary in 2025, the New York District proudly joins in celebrating a legacy of engineering excellence that dates back to the...