Background: The L-575 Benton-Washington-McKissock-Buchanan-Atchison-Hamburg Levee System experienced significant damage during the 2019 Flood Event. This led to seven (7) breaches, along with substantial other damages, occurring throughout the Levee System.
Current Action: Two priority breaches that are impacting the I-29 corridor have been identified for initial repairs. These two construction contracts were awarded on 14 and 19 Apr 2019. The OSRT is also working an overall plan for rehabilitating the levee system. 
Next Steps:
  1. Provide an interim level of flood risk reduction at both initial breach repair locations.
  2. Conduct physical damage assessment when water levels recede and the levees are accessible
  3. Design and construct levee rehabilitation to authorized level of flood risk management.

NOAA River Level Observations & Forecasts

L575 Levee Imagery

The U.S. Army Corps of Engineers, Omaha District completes an initial breach closure on levee L575 near Percival, IA June 20, 2019.
The U.S. Army Corps of Engineers, Omaha District completes an initial breach closure on levee L575 near Percival, IA June 20, 2019.
The U.S. Army Corps of Engineers, Omaha District completes an initial breach closure on levee L575 near Percival, IA June 20, 2019.
The U.S. Army Corps of Engineers, Omaha District completes an initial breach closure on levee L575 near Percival, IA June 20, 2019.
USACE contractors at work along levee L575a near Nebraska City, Nebraska May 10, 2019 following March 2019 runoff event.
USACE contractors at work along levee L575a near Nebraska City, Nebraska May 10, 2019 following March 2019 runoff event.
USACE contractors at work along levee L575a near Nebraska City, Nebraska May 10, 2019 following March 2019 runoff event.
Photo documents aerial view of overtopping levee L575 near Nebraska City, Nebraska Mar. 16, 2019, resulting from a major runoff event. (Photo by USACE, Omaha District)
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial view of levee L550 as of June, 11, 2019.
Aerial view of levee L550 as of June, 11, 2019.
The U.S. Army Corps of Engineers, Omaha District completes the initial breach closure on levee L611-614 near Sioux City, Iowa June 12, 2019. The L611-614 Levee System lies directly east of the confluence of the Platte River (River Mile 595).
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
This image from June 22, 2019 shows progress of the water drainage after Levee L575a was closed on June 20.
This image from June 22, 2019 shows progress of the water drainage after Levee L575a was closed on June 20.
This image from June 22, 2019 shows progress of the water drainage after Levee L575a was closed on June 20.
This image from June 22, 2019 shows progress of the water drainage after Levee L575a was closed on June 20.
This image from June 22, 2019 shows progress of the water drainage after Levee L575a was closed on June 20.
This image from June 22, 2019 shows progress of the water drainage after Levee L575a was closed on June 20.
This image from June 22, 2019 shows progress of the water drainage after Levee L575a was closed on June 20.
This image from June 22, 2019 shows progress of the water drainage after Levee L575a was closed on June 20.
This image from June 22, 2019 shows progress of the water drainage after Levee L575a was closed on June 20.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 20, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 20, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 20, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 20, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 20, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 20, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Multiple groins are placed on L-575 to divert the river flow from the levee to allow for continued repairs on Sep. 23, 2019.
L-575 outlet breach "D" closure on Dec. 19, 2019 located on the downstream end of the levee system in northwest Missouri
L-575 outlet breach "D" closure on Dec. 19, 2019 located on the downstream end of the levee system in northwest Missouri
L-575 outlet breach "E" closure on Dec. 19, 2019 located on the downstream end of the levee system in northwest Missouri

Restoration Activities

 
Initial Breach Repair # 1 – West of Thurman, IA
Initial Breach Repair # 2 – West of Hamburg, IA
Contractor
Western Contracting Corp. from Sioux City, IA
Newt Maritime Services from Dubuque, IA
Contract Amount
$7.5 Million
$12 Million
Contract Award
April 14, 2019
April 19, 2019
Construction Start
May 4, 2019
May 4, 2019
Estimated
Completion
 
 

Video Gallery

Video by Staff Sgt. Elizabeth Taranto
Lou Conter Memorial Production
DMA Pacific - Hawaii Media Bureau
April 23, 2024 | 3:18
PEARL HARBOR -- The National Parks Service and Pacific Fleet came together to pay tribute to Louis "Lou" Conter, the last USS Arizona survivor, who passed away April 1st , 2024, at 103-years-old.

After surviving the attack on Pearl Harbor, Lou went on to serve throughout World War II, and later commissioned and became the Navy's very first SERE (survival evasion resistance and escape) officer. He served in the Korean War, and retired as a Lieutenant Commander after 28 years of service.

Lou continued to inspire and educate the communities around him for the rest of his life, and returned to Pearl Harbor for the annual memorial ceremony as often as he could.

In his final appearance at the Pear Harbor Memorial Ceremony of 2023, Lou sent a video message to the audience saying, "There is one thing you've got to remember, and that is to remember Pearl Harbor."

National Parks Service and Pacific Fleet held the memorial service the morning of April 23rd, 2024. Side Boys released a dove, and visitors paid respects by spreading flower petals across the water. Bagpipers volunteered to play at the ceremony and throughout the day on the shore of Ford Island, and National Parks Service rangers raised the flag from half mass for visitors to witness in the afternoon.

Produced by: SSgt Elizabeth Taranto
Video Footage taken by:
MC1 Brandon Williams-Church
SSgt Elizabeth Taranto
IC2 Jessy Adamec
SrA Caroline Strickland
More