L575 Levee Restoration Information - UPDATED 6/8/19

Background: The L-575 Benton-Washington-McKissock-Buchanan-Atchison-Hamburg Levee System experienced significant damage during the 2019 Flood Event. This led to seven (7) breaches, along with substantial other damages, occurring throughout the Levee System.
Current Action: Two priority breaches that are impacting the I-29 corridor have been identified for initial repairs. These two construction contracts were awarded on 14 and 19 Apr 2019. The OSRT is also working an overall plan for rehabilitating the levee system. 
Next Steps:
  1. Provide an interim level of flood risk reduction at both initial breach repair locations.
  2. Conduct physical damage assessment when water levels recede and the levees are accessible
  3. Design and construct levee rehabilitation to authorized level of flood risk management.

NOAA River Level Observations & Forecasts

L575 Levee Imagery

The U.S. Army Corps of Engineers, Omaha District completes an initial breach closure on levee L575 near Percival, IA June 20, 2019.
The U.S. Army Corps of Engineers, Omaha District completes an initial breach closure on levee L575 near Percival, IA June 20, 2019.
The U.S. Army Corps of Engineers, Omaha District completes an initial breach closure on levee L575 near Percival, IA June 20, 2019.
The U.S. Army Corps of Engineers, Omaha District completes an initial breach closure on levee L575 near Percival, IA June 20, 2019.
USACE contractors at work along levee L575a near Nebraska City, Nebraska May 10, 2019 following March 2019 runoff event.
USACE contractors at work along levee L575a near Nebraska City, Nebraska May 10, 2019 following March 2019 runoff event.
USACE contractors at work along levee L575a near Nebraska City, Nebraska May 10, 2019 following March 2019 runoff event.
Photo documents aerial view of overtopping levee L575 near Nebraska City, Nebraska Mar. 16, 2019, resulting from a major runoff event. (Photo by USACE, Omaha District)
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial view of levee L550 as of June, 11, 2019.
Aerial view of levee L550 as of June, 11, 2019.
The U.S. Army Corps of Engineers, Omaha District completes the initial breach closure on levee L611-614 near Sioux City, Iowa June 12, 2019. The L611-614 Levee System lies directly east of the confluence of the Platte River (River Mile 595).
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
Aerial drone footage shows USACE, Omaha District work continuing on levee L575a June 13, 2019.
This image from June 22, 2019 shows progress of the water drainage after Levee L575a was closed on June 20.
This image from June 22, 2019 shows progress of the water drainage after Levee L575a was closed on June 20.
This image from June 22, 2019 shows progress of the water drainage after Levee L575a was closed on June 20.
This image from June 22, 2019 shows progress of the water drainage after Levee L575a was closed on June 20.
This image from June 22, 2019 shows progress of the water drainage after Levee L575a was closed on June 20.
This image from June 22, 2019 shows progress of the water drainage after Levee L575a was closed on June 20.
This image from June 22, 2019 shows progress of the water drainage after Levee L575a was closed on June 20.
This image from June 22, 2019 shows progress of the water drainage after Levee L575a was closed on June 20.
This image from June 22, 2019 shows progress of the water drainage after Levee L575a was closed on June 20.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view showing Levee 575a progress as of June 24, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 20, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 20, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 20, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 20, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 20, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 20, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of breach L575a northwest of Percival, Iowa June 28, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Aerial view of repair working being done at levee breach L575a_1 July 9, 2019.
Multiple groins are placed on L-575 to divert the river flow from the levee to allow for continued repairs on Sep. 23, 2019.
L-575 outlet breach "D" closure on Dec. 19, 2019 located on the downstream end of the levee system in northwest Missouri
L-575 outlet breach "D" closure on Dec. 19, 2019 located on the downstream end of the levee system in northwest Missouri
L-575 outlet breach "E" closure on Dec. 19, 2019 located on the downstream end of the levee system in northwest Missouri

Restoration Activities

 
Initial Breach Repair # 1 – West of Thurman, IA
Initial Breach Repair # 2 – West of Hamburg, IA
Contractor
Western Contracting Corp. from Sioux City, IA
Newt Maritime Services from Dubuque, IA
Contract Amount
$7.5 Million
$12 Million
Contract Award
April 14, 2019
April 19, 2019
Construction Start
May 4, 2019
May 4, 2019
Estimated
Completion
 
 

Video Gallery

Video by Courtesy
Mission Command (JTF-CS/DCRF)
Joint Task Force Civil Support
May 5, 2019 | 5:00
Joint Task Force Civil Support (JTF-CS) provides mission command of the Defense CBRN Response Force (DCRF) during exercise Vibrant Response 2019 (VR - 19). The Vibrant Response command post (CPX) exercise took place at Fort Custer, Mich., and the Michigan State Emergency Operations Center in Lansing. Phase 1 of Guardian Response 19 (GR19) is a field-training exercise linked to VR19 where about 3,500 federal personnel trained in aviation, medical, engineering, logistics, and other life-saving tasks at Muscatatuk Urban Training Center and Camp Atterbury in Indiana. This exercise featured realistic venues and civilian role-players to simulate a demanding disaster environment under the guidance and direction of the task force commander. The annual GR19 helps participants of the VR19 exercise command and control in a realistic, challenging environment.
More

Tags

Fort HoodVa.chemicalRobins AFBKentuckyFt. HoodGa.disaster responseFort StewartVibrant ResponseCBRNDSCAarnorthHurlburtTexasMarylandOhioFort RileyEMEDSFla.U.S. Army NorthcbirfU.S. NORTHCOMU.S. Northern CommandFt. Campbell35th Signal Brigade1st Medical Brigade62nd Engineer Battalion520th Area Support Medical CompanyTask Force MedicalIndian Head36th Engineer Brigade716th Military Police BattalionWright-Patterson AFBKStask force aviationJoint Base Langley-EustisFORCOMJoint Base Lewis McCord129th CSSBTask Force MedFort Hood TexasBiological Incident Response Force63rd Expeditionary Signal Battalion63rd ESBDefense Support of Civil Authoritiesjoint task force civil support84th Training CommandAFRATChemical Biological Radiological Nuclear520th ASMC63rd Chemical CompanyDefense CBRN Response ForceUSARNORTH823rd RED HORSE330th Trans261st Movement Control Team716th MPTask Force Operations52 Combat Communications Squadron1st Cavalry Division Sustainment BrigadeIdentification and Detection226th Composite Supply Companynuclear detonationdemon brigadeGuardian Response602nd Support Maintenance Company274 MCT501st Area Support Medical Company68th Engineer Construction CompanyVibrant Response-Guardian ResponseVR-GRTask Force OpsTask Force LogTask Force AvnTask Force Logistics1st Air Cavalry Brigade Air Cav68ECCJPEO CBRN68 ECC87th Engineer Company181 Double Dragons181st CBRN Company Hazard Response546th ASMC546th Medical Company (Area Support)110th CBRN Battallion172nd chemThe 172D Chemical Company571st Military Police Company Joint Base Lewis-McCord218th Military Police Company Ft. Campbell501ST ASMC104th Engineer Construction Company “Titans”nFt. Hood104 ECCAir Force Radiological Assessment Team1MB Silver KnightsHHC553DHHQ 553 Combat Support Sustainment Brigade523d CTC523 Composite Truck CompanyWash State74th Composite Truck Company Fort Campbell74 CTC567th FRG567th ICTC FRG – Inland Cargo Transportation Company274th Movement Control Team Fort Story61st Movement Control Team330th TRANS BNFt Gordentechnical search and rescuemass casualty deconmission command CBRNinteragency CBRN
More