Garrison Project hosts industry day for largest dam safety modification project in USACE history

USACE OMAHA DISTRICT
Published Oct. 19, 2023
A photo of USACE personnel and contractors at the Garrison Dam Project.

Engineers from the U.S. Army Corps of Engineers, Omaha District provide a tour to contractors attending an industry day for the Garrison Dam spillway modification project near Riverdale, North Dakota, October 11, 2023. The multi-year project is considered to be the largest dam safety modification project in U.S. Army Corps of Engineers history. (U.S. Army photo by Delanie Stafford)

A photo of USACE personnel and contractors at the Garrison Dam Project.

Chad Vensel, a hydraulic engineer with the U.S. Army Corps of Engineers, Omaha District, briefs contractors attending an industry day for the Garrison Dam spillway modification project near Riverdale, North Dakota, October 11, 2023. The multi-year project is considered to be the largest dam safety modification project in U.S. Army Corps of Engineers history. (U.S. Army photo by Delanie Stafford)

A photo of USACE personnel and contractors at the Garrison Dam Project.

Engineers from the U.S. Army Corps of Engineers, Omaha District provide a tour to contractors attending an industry day for the Garrison Dam spillway modification project near Riverdale, North Dakota, October 11, 2023. The multi-year project is considered to be the largest dam safety modification project in U.S. Army Corps of Engineers history. (U.S. Army photo by Delanie Stafford)

A photo of USACE personnel and contractors at the Garrison Dam Project.

Engineers from the U.S. Army Corps of Engineers, Omaha District provide a tour to contractors attending an industry day for the Garrison Dam spillway modification project near Riverdale, North Dakota, October 11, 2023. The multi-year project is considered to be the largest dam safety modification project in U.S. Army Corps of Engineers history. (U.S. Army photo by Delanie Stafford)

A photo of USACE personnel and contractors at the Garrison Dam Project.

Todd Lindquist, the Garrison Dam operations project manager for the U.S. Army Corps of Engineers, Omaha District, provides a briefing during an industry day for the Garrison Dam spillway modification project near Riverdale, North Dakota, October 11, 2023. The multi-year project is considered to be the largest dam safety modification project in U.S. Army Corps of Engineers history. (U.S. Army photo by Delanie Stafford)

A photo of USACE personnel and contractors at the Garrison Dam Project.

Col. Robert Newbauer, U.S. Army Corps of Engineers, Omaha District commander, provides opening remarks to contractors attending an industry day for the Garrison Dam spillway modification project at the city hall in Pick City, North Dakota, October 11, 2023. The multi-year project is considered to be the largest dam safety modification project in U.S. Army Corps of Engineers history. (U.S. Army photo by Delanie Stafford)

RIVERDALE, N.D. - Contractors from 10 construction and engineering firms attended an industry day Oct. 11 at the Garrison Dam located between Riverdale and Pick City, North Dakota. The industry day was part of early planning efforts for a U.S. Army Corps of Engineers multi-year project considered to be the largest dam safety modification project in USACE history.

The project will modernize the dam and reduce risks associated with the spillway’s performance when used to reduce flooding and balance river flows in the Upper Missouri River basin during significant storms or snowmelt.

“The dam, built in the 1950’s, was not originally designed for the reservoir elevations and spillway releases that would be expected under today’s conditions,” said Andrew Barry, chief of the USACE Omaha District’s Dam Safety Production Center. “Modifying the spillway and other structural work will help ensure the dam and spillway can be operated at the full range of potential flows and continue to reduce the impact of flooding on people and property downstream of the dam.”

Concerns with the spillway were identified during dam safety inspections following record runoff into the Upper Missouri River Basin and Lake Sakakawea in 2011. High water levels in Lake Sakakawea required the opening of the dam’s spillway gates for flood risk management purposes for the first time since the dam became operational in 1955. The peak flow of about 60,000 cubic feet per second of water released through the spillway created a high pressurization of the spillway’s subdrainage system that caused damage to the system and concrete within the spillway chute.

Barry explains that the modifications primarily focus on critical spillway components, including the spillway’s Tainter gates, abutments, areas behind the spillway chute walls, drainage pipes, chute slab and stilling basin. Modifications also include new seepage drains on the embankment near the dam’s powerhouse.

Barry added that while these modifications will improve conditions at the dam, no dam is risk-free and no dam can eliminate flooding.

“Flooding can still occur, even when a dam performs as it was designed,” he said. “It’s important for people to understand the risks associated with living downstream of a dam.”

The industry day provided an opportunity for contractors interested in bidding on the modification project and working with USACE to tour the spillway and learn more about the scope of construction and its unique challenges.

“Two of the biggest challenges are the shorter construction seasons in North Dakota due to severe winters, and that much of the construction will occur in the emergency spillway,” said Jeff Greenwald, a planner and project manager with the USACE Omaha District. “We need to plan for the possibility of using the spillway in a high runoff season which could coincide with the construction season. The contractor would have a short period to close down their work before the impending spillway operation. This coordination with construction contractors during the design phase benefits the project.”

The modification project is currently in the pre-construction engineering and design phase. Construction is expected to begin around 2029 and take approximately six years.

Garrison Dam is one of six USACE mainstem dams on the Upper Missouri River. Lake Sakakawea behind the dam is the third largest reservoir in the United States and the largest reservoir operated by USACE with a current capacity of 23.5 million acre-feet.

The Garrison Dam and Lake Sakakawea Project was authorized by the Flood Control Act in 1944 as part of the general comprehensive plan for flood risk management, hydroelectric power, water supply, water quality, irrigation, recreation, navigation, and fish and wildlife conservation in the Missouri River Basin.

To learn about the USACE Dam Safety Program, visit https://www.nwo.usace.army.mil/Missions/Civil-Works/Dam-and-Levee-Safety/.


News from around USACE

Leading the charge against the June 2024 Missouri River floods
7/15/2024
When the Missouri River and its tributaries rose above flood stage in late June, the damaging flood waters required an aggressive response and the U.S. Army Corps of Engineers, Omaha District led the...
Gathright Dam pulse release set for Wednesday
7/15/2024
NORFOLK – The U.S. Army Corps of Engineers Norfolk District will conduct a pulse release at Gathright Dam, near Covington, Va., Wednesday, July 17 beginning at approximately 6 a.m...
Connor Foster is continuing his journey and career where it all began
7/15/2024 UPDATED
After spending a summer as a student intern with the U.S. Army Corps of Engineers, Buffalo District in 2023, Connor Foster was hooked and decided to take his career further and join the Buffalo...
Walla Walla District Welcomes New Commander
7/15/2024 UPDATED
The Walla Walla District of the U.S. Army Corps of Engineers (USACE) held a change of command ceremony where Lt. Col. ShaiLin KingSlack relinquished command to Lt. Col. Katie Werback at the Marcus...