Florence bedrock removal project on Missouri River in full swing

USACE Omaha
Published May 26, 2022
Updated: May 26, 2022
On site at the U.S. Army Corps of Engineers, Omaha District Florence bedrock removal project on the Missouri River, May 18, 2022.

On site at the U.S. Army Corps of Engineers, Omaha District Florence bedrock removal project on the Missouri River, May 18, 2022. The goal of the project is to excavate a minimum of 120,000 cubic yards of material, and restore adequate channel parameters for river boat traffic on the Missouri River. (U.S. Army Corps of Engineers Photo by Samuel Weldin)

Christopher Svendsen, Hydraulic Engineer, US Army Corps of Engineers, Omaha District, and others make their way to the Florence bedrock removal project on the Missouri River, May 18, 2022.

Christopher Svendsen, Hydraulic Engineer, US Army Corps of Engineers, Omaha District, and others make their way to the Florence bedrock removal project on the Missouri River, May 18, 2022. The goal of the project is to excavate a minimum of 120,000 cubic yards of material, and restore adequate channel parameters for river boat traffic on the Missouri River. (U.S. Army Corps of Engineers Photo by Samuel Weldin)

On site at the US Army Corps of Engineers, Omaha District Florence bedrock removal project on the Missouri River, May 18, 2022.

On site at the US Army Corps of Engineers, Omaha District Florence bedrock removal project on the Missouri River, May 18, 2022. The goal of the project is to excavate a minimum of 120,000 cubic yards of material, and restore adequate channel parameters for river boat traffic on the Missouri River. (U.S. Army Corps of Engineers Photo by Samuel Weldin)

On site at the US Army Corps of Engineers, Omaha District Florence bedrock removal project on the Missouri River, May 18, 2022.

On site at the US Army Corps of Engineers, Omaha District Florence bedrock removal project on the Missouri River, May 18, 2022. The goal of the project is to excavate a minimum of 120,000 cubic yards of material, and restore adequate channel parameters for river boat traffic on the Missouri River. (U.S. Army Corps of Engineers Photo by Samuel Weldin)

On site at the U.S. Army Corps of Engineers, Omaha District Florence bedrock removal project on the Missouri River, May 18, 2022.

On site at the U.S. Army Corps of Engineers, Omaha District Florence bedrock removal project on the Missouri River, May 18, 2022. The goal of the project is to excavate a minimum of 120,000 cubic yards of material, and restore adequate channel parameters for river boat traffic on the Missouri River. (U.S. Army Corps of Engineers Photo by Samuel Weldin)

OMAHA, Neb. -- Work is well underway as the U.S. Army Corps of Engineers, Omaha District, in partnership with our contractors and sub-contractors, are excavating bed rock from the Florence Bend reach portion of the Missouri River near Omaha. 

The implementation of the excavation is due to riverbed degradation in recent years, which has lowered water elevation at certain river stages through this reach of the river. This has resulted in insufficient navigation channel dimensions at several locations within Florence Bend. The shallow depths add risk or hinder passage to the nearly five million tons of cargo moving along the Missouri River annually. The goal is to excavate a minimum of 120,000 cubic yards of material, and restore adequate channel parameters for river traffic, by contracts end.

“The navigation channel has experienced some degradation over the past few decades due to all the floods that have happened, and the purpose of this project is to restore the draft for the tows to come through, with the goal being to get back to a 300-foot width and nine-foot depth authorized navigation channel,” Daniel Pridal, Omaha district engineer, said. “We’ve got about 120,000 yards of material to remove and, so far, pretty good progress, but that’s the reason we are out here inspecting the process and following up on it.”

The process to achieve this goal includes excavating high pinnacles of bed rock from the Missouri River one mile downstream of the Mormon Bridge, transporting the rock upstream on barges, and placing that excavated rock on revetments. By bolstering these revetments, this can prevent or minimize future damage during periods of floods or heavy seasonal rains. The bedrock is being moved at a pace of 2000 tons a day and operations run 12 hours a day, seven days a week.

This operation is being executed as a part of ongoing maintenance of the navigation channel, which begins at the mouth of the Missouri River at St Louis, Missouri and extends upstream for 734 miles to Sioux City, Iowa.

The base contract of this $8.2 million project is scheduled to be complete at the end of May, with option one and two portions completed in October 2022.

For additional information on the District’s Missouri River projects visit: https://www.nwo.usace.army.mil/Missions/Dam-and-Lake-Projects/Missouri-River-Navigation/


News from around USACE

The Corps Environment – Spring 2025 edition now available
5/23/2025
The Spring 2025 edition of The Corps Environment is now available! This publication highlights how the U.S. Army Corps of Engineers is turning environmental challenges into mission-ready solutions...
Nashville District highlights contracting opportunities at small business event
5/23/2025
On May 20, 2025, small businesses gathered at Tennessee State University for BIZGOV Connect, a networking event focused on entering government contracting. The U.S. Army Corps of Engineers Nashville...
USACE Completes Two-Week Regional Power Mission Exercise, Prepares for Upcoming Hurricane Season
5/22/2025
The U.S. Army Corps of Engineers (USACE) successfully concluded a two-week Regional Power Mission Exercise on May 16, enhancing its readiness to provide critical temporary emergency power in the wake...
A Legacy that Floats: Remembering Staff Sgt. Dustin Wright
5/22/2025
“My brother somehow managed to always keep an open heart and cared deeply for others. Those qualities shone throughout his life and in his passing,” said Will Wright. “Even in his final moment, he...