Florence bedrock removal project on Missouri River in full swing

USACE Omaha
Published May 26, 2022
Updated: May 26, 2022
On site at the U.S. Army Corps of Engineers, Omaha District Florence bedrock removal project on the Missouri River, May 18, 2022.

On site at the U.S. Army Corps of Engineers, Omaha District Florence bedrock removal project on the Missouri River, May 18, 2022. The goal of the project is to excavate a minimum of 120,000 cubic yards of material, and restore adequate channel parameters for river boat traffic on the Missouri River. (U.S. Army Corps of Engineers Photo by Samuel Weldin)

Christopher Svendsen, Hydraulic Engineer, US Army Corps of Engineers, Omaha District, and others make their way to the Florence bedrock removal project on the Missouri River, May 18, 2022.

Christopher Svendsen, Hydraulic Engineer, US Army Corps of Engineers, Omaha District, and others make their way to the Florence bedrock removal project on the Missouri River, May 18, 2022. The goal of the project is to excavate a minimum of 120,000 cubic yards of material, and restore adequate channel parameters for river boat traffic on the Missouri River. (U.S. Army Corps of Engineers Photo by Samuel Weldin)

On site at the US Army Corps of Engineers, Omaha District Florence bedrock removal project on the Missouri River, May 18, 2022.

On site at the US Army Corps of Engineers, Omaha District Florence bedrock removal project on the Missouri River, May 18, 2022. The goal of the project is to excavate a minimum of 120,000 cubic yards of material, and restore adequate channel parameters for river boat traffic on the Missouri River. (U.S. Army Corps of Engineers Photo by Samuel Weldin)

On site at the US Army Corps of Engineers, Omaha District Florence bedrock removal project on the Missouri River, May 18, 2022.

On site at the US Army Corps of Engineers, Omaha District Florence bedrock removal project on the Missouri River, May 18, 2022. The goal of the project is to excavate a minimum of 120,000 cubic yards of material, and restore adequate channel parameters for river boat traffic on the Missouri River. (U.S. Army Corps of Engineers Photo by Samuel Weldin)

On site at the U.S. Army Corps of Engineers, Omaha District Florence bedrock removal project on the Missouri River, May 18, 2022.

On site at the U.S. Army Corps of Engineers, Omaha District Florence bedrock removal project on the Missouri River, May 18, 2022. The goal of the project is to excavate a minimum of 120,000 cubic yards of material, and restore adequate channel parameters for river boat traffic on the Missouri River. (U.S. Army Corps of Engineers Photo by Samuel Weldin)

OMAHA, Neb. -- Work is well underway as the U.S. Army Corps of Engineers, Omaha District, in partnership with our contractors and sub-contractors, are excavating bed rock from the Florence Bend reach portion of the Missouri River near Omaha. 

The implementation of the excavation is due to riverbed degradation in recent years, which has lowered water elevation at certain river stages through this reach of the river. This has resulted in insufficient navigation channel dimensions at several locations within Florence Bend. The shallow depths add risk or hinder passage to the nearly five million tons of cargo moving along the Missouri River annually. The goal is to excavate a minimum of 120,000 cubic yards of material, and restore adequate channel parameters for river traffic, by contracts end.

“The navigation channel has experienced some degradation over the past few decades due to all the floods that have happened, and the purpose of this project is to restore the draft for the tows to come through, with the goal being to get back to a 300-foot width and nine-foot depth authorized navigation channel,” Daniel Pridal, Omaha district engineer, said. “We’ve got about 120,000 yards of material to remove and, so far, pretty good progress, but that’s the reason we are out here inspecting the process and following up on it.”

The process to achieve this goal includes excavating high pinnacles of bed rock from the Missouri River one mile downstream of the Mormon Bridge, transporting the rock upstream on barges, and placing that excavated rock on revetments. By bolstering these revetments, this can prevent or minimize future damage during periods of floods or heavy seasonal rains. The bedrock is being moved at a pace of 2000 tons a day and operations run 12 hours a day, seven days a week.

This operation is being executed as a part of ongoing maintenance of the navigation channel, which begins at the mouth of the Missouri River at St Louis, Missouri and extends upstream for 734 miles to Sioux City, Iowa.

The base contract of this $8.2 million project is scheduled to be complete at the end of May, with option one and two portions completed in October 2022.

For additional information on the District’s Missouri River projects visit: https://www.nwo.usace.army.mil/Missions/Dam-and-Lake-Projects/Missouri-River-Navigation/


News from around USACE

USACE refreshes fish attractor sites at J. Strom Thurmond Lake
2/6/2026
The U.S. Army Corps of Engineers’ Savannah District recently refreshed five fish attractor sites in J. Strom Thurmond Lake, also known as Clarks Hill Lake. The Savannah District maintains a network of...
USACE employees rescue Mississippi motorist during winter storm response
2/6/2026
While on one emergency response mission, two U.S. Army Corps of Engineers employees found themselves in the middle of another...
Modernizing the mission: New hygiene facility at Fort Knox supports Army readiness
2/6/2026
For the thousands of U.S. Army ROTC cadets who converge on Fort Knox every summer, the "CST” or Cadet Summer Training experience is a rite of passage. According to the U.S. Army Cadet Command, the...
ITL finds success in DARPA partnership
2/5/2026 UPDATED
Partnerships are a cornerstone of the U.S. Army Engineer Research and Development Center’s mission to deliver cutting-edge science and engineering solutions for the nation. One such partnership...