US Army Corps of Engineers
Omaha District

Western Sarpy Levee Restoration Information

Background: The Western Sarpy – Platte River Left Bank Levee System was damaged during the 2019 Flood Event, leading to the Levee Sponsor submitting a Public Law (PL) 84-99 Rehabilitation Assistance request to the US Army Corps of Engineers – Omaha District.

Current Action:  Complete the levee repair construction contract.

Restoration Activities:

 

Full Repair Contract 

Contractor

Valley Corporation from Valley, NE

Contract Amount

$4.2 Million

Contract Award

September 25, 2019

  Construction Start

November 4, 2019

Estimated Completion

Early February 2019

 

 

 

 

 

 

 

 

Next Step: Repair the levee system to its authorized level of flood risk management.

Status Updates:

08 November 2019 - The contractor mobilized to the project site on 04 November 2019 and has begun work on levee repairs.

24 October 2019 - The contractor is scheduled to mobilize to the project site on 28 October 2019 to begin repairs.

13 October 2019 - A pre-construction team meeting was held on Oct. 9, 2019, and the contractor was issued notice to proceed with repairs.  The contractor is preparing to mobilize to begin construction.

27 September 2019 – The levee repair contract was awarded to Valley Corporation of Valley, NE on 25 September 2019 in the amount of $4,235,783 with a period of performance of 120 calendar days.

13 September 2019 – The team is currently awaiting construction funds from USACE HQ. Once funds are received, the team anticipates awarding a construction contract by the end of the month.

04 September 2019 – Correction. The bid opening occurred on 03 September 2019 and the construction contract is anticipated to be awarded in the next few weeks.

29 August 2019 – The site walk with contractors was conducted on 29 August 2019. The contract will be awarded 03 September 2019. 

23 August 2019 – A construction contract to repair the Western Sarpy levee system was advertised to pre-qualified contractors on 19 August 2019 with award anticipated around 03 September 2019. 

05 Aug 2019 – The USACE Design team and Levee Sponsor conducted a “Plan In-Hand” review of the repair design documents on 24 July 2019. These reviews are conducted to ensure that the team is developing a technically feasible and acceptable design. Engineering and Design (E&D) work continues for rehabilitating the Western Sarpy levee system. The team is still anticipating to be done with the E&D process by early fall.

08 July 2019 – Engineering and Design (E&D) work is on-going for rehabilitating the Western Sarpy project. The team is anticipating to be done with the E&D process by late summer or early fall.

15 June 2019 – An initial site damage assessment and economic analysis has been completed. From this initial assessment the USACE team has determined that there are damages to the levee system that are eligible for PL 84-99 Rehabilitation Assistance. 

NOAA River Level Observations & Forecasts

NOAA Water Gauge Levels

Western Sarpy Imagery

USACE contractors discuss repairs during the pre-bid site visit conducted at Western Sarpy Aug. 28, 2019.
USACE contractors inspect the riverbank of the levee system during the pre-bid site visit conducted at Western Sarpy Aug. 28, 2019.
Photo documents overtopping of Western Sarpy levee in Western Sarpy, Nebraska Mar. 14, 2019, resulting from major runoff event earlier in month. (Photo by USACE, Omaha District)
Photo documents overtopping of Western Sarpy levee in Western Sarpy, Nebraska Mar. 14, 2019, resulting from major runoff event earlier in month. (Photo by USACE, Omaha District)
Photo documents overtopping of Western Sarpy levee in Western Sarpy, Nebraska Mar. 14, 2019, resulting from major runoff event earlier in month. (Photo by USACE, Omaha District)

Video Gallery