Background: The Sheridan – Little Goose Creek Left Bank and Big Goose Creek Right Bank Levee System were damaged during the 2019 Flood Event, leading to the Levee Sponsor submitting a Public Law (PL) 84-99 Rehabilitation Assistance request to the US Army Corps of Engineers – Omaha District.

 

Current Action:  Finalizing the damage assessment and economic analysis report.  This will allow the USACE team to communicate to the sponsor if any damages to the Sheridan levee system are eligible for PL 84-99 Rehabilitation Assistance

Next Steps:

  1. Communicate to the Sponsor the findings of the initial site damage assessment and economic analysis.
  2. If repairs are eligible for PL 84-99 Rehabilitation Assistance, then design funding will be requested.
  3. If repairs are not PL 84-99 Rehabilitation Assistance, then the USACE team will work with the Sponsor to determine if technical assistance is desired to help repair the damaged levee system.

Status Updates:

08 November 2019 -  Funding has been received to begin the design process for the Sheridan levee repair project.

24 October 2019 -  The damage assessment and economic analysis report has been approved, and the team has requested funding to begin work on engineering and design of the levee repairs.

13 October 2019 -  The team received comments from Northwestern Division on the damage assessment and economic analysis report and is now working to respond to these comments and finalize the documentation.  This documentation will be utilized to make a final determination on eligibility for PL 84-99 rehabilitation assistance.

27 September 2019 – The team continues to finalize the damage assessment and economic analysis report in order to make a final determination on eligibility for PL 84-99 rehabilitation assistance.

13 September 2019 – The team is targeting the end of the month to have the damage assessment and economic analysis report finalized in order to make a final determination on eligibility for PL 84-99 rehabilitation assistance.

06 September 2019 – The team is still finalizing the damage assessment and economic analysis report in order to make a final determination on eligibility for PL 84-99 rehabilitation assistance.  It is anticipated that this analysis and documentation will be done by the end of the month.

29 August 2019 – The team continues to finalize the damage assessment and economic analysis report in order to make a final determination on eligibility for PL 84-99 rehabilitation assistance.

05 August 2019 – The team continues to finalize the damage assessment and economic analysis report to make a final determination on eligibility for PL 84-99 Rehabilitation Assistance.

01 August 2019 – An initial site damage assessment been completed. The team is finalizing the damage assessment and economic analysis report to make a final determination on eligibility for PL 84-99 Rehabilitation Assistance.