Sheridan Levee Restoration Information

Background: The Sheridan – Little Goose Creek Left Bank and Big Goose Creek Right Bank Levee System were damaged during the 2019 Flood Event, leading to the Levee Sponsor submitting a Public Law (PL) 84-99 Rehabilitation Assistance request to the US Army Corps of Engineers – Omaha District.

Current Action: Complete punch list items and contract close-out.

Restoration Activities:

 

Full Repair Contract 

Contractor

Relyant Global LLC from Maryville, TN

Contract Amount

$3.5 million

Contract Award

July 24, 2020

  Construction Start

August 17, 2020

Completion

November 21, 2020

 

 

 

 

 

 

 

 

 

Status Updates:

03 February 2021 - The levee repair project was completed on 21 November 2020. The team is working through the contract close-out process and punch list items.

08 September 2020 - The levee repair contract was awarded on 24 July 2020 and the contractor mobilized on 17 August 2020. Levee repairs are approximately 15 percent complete.

16 July 2020 - The levee repair contract was advertised on 19 June 2020 with a virtual site visit on 24 June 2020. Proposals were received on 08 July 2020 and the team is currently evaluating those proposals.

10 June 2020 - The team is working with the levee sponsor to secure the final real estate access to complete the levee repair project. Once access is finalized, the contract will be advertised.

08 May 2020 - The team is working with the levee sponsor to secure all of the necessary real estate access to complete the levee repair project.

23 April 2020 - The team is working with the levee sponsor to secure all of the necessary real estate access to complete the levee repair project.

10 April 2020 - The team continues to work the design process for this levee repair project.

16 March 2020 - The team continues to work the design process for this levee repair project.

04 March 2020 - The team continues to work the design process for this levee repair project.

13 February 2020 -  The team is continuing to work the design process for the Sheridan levee repair project.

31 January 2020 -  The USACE team is working with the levee sponsor to develop a design and construction schedule for this levee repair project.

10 January 2020 -  The USACE team is working with the levee sponsor to develop a design and construction schedule for this levee repair project.

18 December 2019 -  The USACE team is working with the levee sponsor to develop a design and construction schedule for this levee repair project.

06 December 2019 -  The USACE team is working to develop a design schedule for this levee repair project.

22 November 2019 -  The USACE team is working to develop a design schedule for this levee repair project.

08 November 2019 -  Funding has been received to begin the design process for the Sheridan levee repair project.

24 October 2019 -  The damage assessment and economic analysis report has been approved, and the team has requested funding to begin work on engineering and design of the levee repairs.

13 October 2019 -  The team received comments from Northwestern Division on the damage assessment and economic analysis report and is now working to respond to these comments and finalize the documentation.  This documentation will be utilized to make a final determination on eligibility for PL 84-99 rehabilitation assistance.

27 September 2019 – The team continues to finalize the damage assessment and economic analysis report in order to make a final determination on eligibility for PL 84-99 rehabilitation assistance.

13 September 2019 – The team is targeting the end of the month to have the damage assessment and economic analysis report finalized in order to make a final determination on eligibility for PL 84-99 rehabilitation assistance.

06 September 2019 – The team is still finalizing the damage assessment and economic analysis report in order to make a final determination on eligibility for PL 84-99 rehabilitation assistance.  It is anticipated that this analysis and documentation will be done by the end of the month.

29 August 2019 – The team continues to finalize the damage assessment and economic analysis report in order to make a final determination on eligibility for PL 84-99 rehabilitation assistance.

05 August 2019 – The team continues to finalize the damage assessment and economic analysis report to make a final determination on eligibility for PL 84-99 Rehabilitation Assistance.

01 August 2019 – An initial site damage assessment been completed. The team is finalizing the damage assessment and economic analysis report to make a final determination on eligibility for PL 84-99 Rehabilitation Assistance.