Cedar Creek Omaha (F&W) Restoration Information

Background: The Cedar Creek (Omaha F&W) – Platte River Right Bank Levee System was damaged during the 2019 Flood Event, leading to the Project Sponsor submitting a Public Law (PL) 84-99 Rehabilitation Assistance request to the US Army Corps of Engineers – Omaha District.

Current Action: Close out the construction contract.

Restoration Activities:

 

Full Repair Contract 

Contractor

Midwest Construction from Nebraska City, NE

Contract Amount

$1,343,000

Contract Award

October 4, 2019

  Construction Start

Late October 2019

Completion

December 12, 2019

 

 

 

 

 

 

 

 

 

Status Updates:

10 January 2020 - Work on the Cedar Creek levee repair contract is complete.

18 December 2019 - Work on the Cedar Creek levee repair contract is complete with final inspection occurring on 12 December 2019. The team is currently working on closing out the contract.

06 December 2019 - The contractor is currently 97 percent complete with levee repair work. The pre-final inspection was conducted on 25 November 2019 with final inspection tentatively scheduled for the week of 09 December 2019.

22 November 2019 - The contractor is placing riprap and bedding materials at two of the three damage locations, seeding the third damage location and is expected to be substantially complete with repairs by the end of the month.

08 November 2019 - The contractor mobilized to the site on 30 October 2019 and has begun work on repairing the levee.

24 October 2019 - The pre-construction team meeting was held on 16 October 2019 with notice to proceed issued on the same day. The contractor is scheduled to mobilize to the site to begin repairs on 28 October 2019.

13 October 2019 - Pre-construction team meeting is scheduled for the week of 14 October 2019, at which time it is anticipated notice to proceed with repairs will be issued and the contractor can begin the repair work.

04 October 2019 – The levee repair contract was awarded to Midwest Construction of Nebraska City, NE in the amount of $1,343,000 on 04 October 2019. The repair is estimated to be complete in mid April 2020.

27 September 2019 – Funds to repair the Cedar Creek levee system have been received. The construction contract is scheduled to be awarded by 04 October 2019.

13 September 2019 – The bid opening occurred on 04 Sep 2019. It is anticipated that this project will be awarded within a few weeks, pending receipt of project funding from USACE HQ.

04 September 2019 – Correction. The bid opening was conducted on 04 Sep 2019 and the team is anticipating awarding the construction contract by mid-to-late September. 

29 August 2019 – A construction contract to repair the Cedar Creek levee system was advertised to pre-qualified contractors on 21 August 2019 with award anticipated around 04 September 2019.  The pre-qualified contractors conducted a site visit on 29 August 2019 to view the scope of work on site in order to make an accurate bid.

23 August 2019 – The team is on scheduled to be done with the E&D process late summer. The project was advertised to the pre-qualified Contractor Pool on 21 August 2019 with award anticipated around 04 September 2019.

05 August 2019 – Engineering and Design (E&D) work continues for rehabilitating the Cedar Creek levee system. The team is still anticipating to be done with the E&D process by late summer.

16 July 2019 – An initial site damage assessment and economic analysis has been completed.  From this initial assessment the USACE team has determined that there are damages to the levee system that are eligible for PL 84-99 Rehabilitation Assistance. Engineering and Design (E&D) work is on-going for rehabilitating the Cedar Creek Levee System.  The team is anticipating to be done with the E&D process for repairing the damage identified by the late-summer 2019.

NOAA River Level Observations & Forecasts

NOAA Water Gauge Levels

Cedar Creek Omaha (F&W) Levee Imagery

Final inspection of Cedar Creek levee repair, Dec. 12, 2019
USACE Engineering and Construction Team and the Local Levee Sponsor conducting the Plan In-Hand Review on the Cedar Creek Levee Aug. 7, 2019.
Erosion and scour along the riverside channel bank extending into the levee section at Cedar Creek levee May 16, 2019.
Minor damage to the levee crest due to high water overtopping the Cedar Creek levee May 16, 2019.
Pre-qualified contractors conduct a site visit at the Cedar Creek levee on Aug. 29, 2019 to view the scope of work on site in order to make an accurate bid.

Video Gallery

Video by Curtis Keester
Carlisle Barracks Disinterment Project Findings
U.S. Army Garrison Carlisle Barracks
Sept. 21, 2023 | 11:56
Carlisle Barracks Disinterment Project Findings

CARLISLE, Pa. – The U.S. Army finalized its sixth disinterment project, returning four Native American children to their families. These children died after being sent to the Carlisle Indian Industrial School and were buried there more than 100 years ago.

The Office of Army Cemeteries (OAC) presented their findings today from the multi-phase disinterment project with archaeological and anthropological expertise from the U.S. Army Corps of Engineers.

The OAC team's findings of the human remains found in the gravesites assigned to Beau Neal (Northern Arapaho), Launy Shorty (Blackfeet), Amos Lafromboise (Sisseton Wahpeton Oyate) and Edward Upright (Spirit Lake) were biologically consistent with the information contained in their student and burial location records.

Each child was returned to their family in a dignified transfer ceremony, and several have already been reinterred on their native lands.

On Sept.14, the Army conducted a dignified disinterment of grave E-14 at the Carlisle Post Cemetery, which records indicated was for a Puyallup child, Edward Spott. The remains recovered however were inconsistent with that of an approximately 17–18-year-old male and instead found to be that of an approximately 16–22-year-old female. The unknown remains were reinterred in a dignified ceremony on Saturday, Sept. 15 with the caring assistance and compassion of the Puyallup family. The Army is committed to reviewing all available resources and seeking new information that may help us identify any possible error that led to this anomaly so we can make the appropriate effort to return Edward to his family and the Puyallup Tribe.

“The Army is truly saddened we were unable to return Eddie to his family this year,” said Karen Durham-Aguilera, Executive Director, Office of Army Cemeteries and Arlington National Cemetery.

“We remain honored to have had the opportunity to work with these Native American families and to help them find closure. On behalf of my team, I would like to thank all of the families for placing their trust in us throughout this journey in returning their children home.”

In 1879, Carlisle Barracks became the site of the Carlisle Indian Industrial School, operated by the Department of the Interior until 1918. The school educated more than 10,000 Native American children, with representation from approximately 50 Native American tribes from across the nation.

The Carlisle Barracks Post Cemetery will re-open to visitors starting Friday, Sept. 21.
More