Cedar Creek Omaha (F&W) Restoration Information

Background: The Cedar Creek (Omaha F&W) – Platte River Right Bank Levee System was damaged during the 2019 Flood Event, leading to the Project Sponsor submitting a Public Law (PL) 84-99 Rehabilitation Assistance request to the US Army Corps of Engineers – Omaha District.

Current Action: Close out the construction contract.

Restoration Activities:

 

Full Repair Contract 

Contractor

Midwest Construction from Nebraska City, NE

Contract Amount

$1,343,000

Contract Award

October 4, 2019

  Construction Start

Late October 2019

Completion

December 12, 2019

 

 

 

 

 

 

 

 

 

Status Updates:

10 January 2020 - Work on the Cedar Creek levee repair contract is complete.

18 December 2019 - Work on the Cedar Creek levee repair contract is complete with final inspection occurring on 12 December 2019. The team is currently working on closing out the contract.

06 December 2019 - The contractor is currently 97 percent complete with levee repair work. The pre-final inspection was conducted on 25 November 2019 with final inspection tentatively scheduled for the week of 09 December 2019.

22 November 2019 - The contractor is placing riprap and bedding materials at two of the three damage locations, seeding the third damage location and is expected to be substantially complete with repairs by the end of the month.

08 November 2019 - The contractor mobilized to the site on 30 October 2019 and has begun work on repairing the levee.

24 October 2019 - The pre-construction team meeting was held on 16 October 2019 with notice to proceed issued on the same day. The contractor is scheduled to mobilize to the site to begin repairs on 28 October 2019.

13 October 2019 - Pre-construction team meeting is scheduled for the week of 14 October 2019, at which time it is anticipated notice to proceed with repairs will be issued and the contractor can begin the repair work.

04 October 2019 – The levee repair contract was awarded to Midwest Construction of Nebraska City, NE in the amount of $1,343,000 on 04 October 2019. The repair is estimated to be complete in mid April 2020.

27 September 2019 – Funds to repair the Cedar Creek levee system have been received. The construction contract is scheduled to be awarded by 04 October 2019.

13 September 2019 – The bid opening occurred on 04 Sep 2019. It is anticipated that this project will be awarded within a few weeks, pending receipt of project funding from USACE HQ.

04 September 2019 – Correction. The bid opening was conducted on 04 Sep 2019 and the team is anticipating awarding the construction contract by mid-to-late September. 

29 August 2019 – A construction contract to repair the Cedar Creek levee system was advertised to pre-qualified contractors on 21 August 2019 with award anticipated around 04 September 2019.  The pre-qualified contractors conducted a site visit on 29 August 2019 to view the scope of work on site in order to make an accurate bid.

23 August 2019 – The team is on scheduled to be done with the E&D process late summer. The project was advertised to the pre-qualified Contractor Pool on 21 August 2019 with award anticipated around 04 September 2019.

05 August 2019 – Engineering and Design (E&D) work continues for rehabilitating the Cedar Creek levee system. The team is still anticipating to be done with the E&D process by late summer.

16 July 2019 – An initial site damage assessment and economic analysis has been completed.  From this initial assessment the USACE team has determined that there are damages to the levee system that are eligible for PL 84-99 Rehabilitation Assistance. Engineering and Design (E&D) work is on-going for rehabilitating the Cedar Creek Levee System.  The team is anticipating to be done with the E&D process for repairing the damage identified by the late-summer 2019.

NOAA River Level Observations & Forecasts

NOAA Water Gauge Levels

Cedar Creek Omaha (F&W) Levee Imagery

Final inspection of Cedar Creek levee repair, Dec. 12, 2019
USACE Engineering and Construction Team and the Local Levee Sponsor conducting the Plan In-Hand Review on the Cedar Creek Levee Aug. 7, 2019.
Erosion and scour along the riverside channel bank extending into the levee section at Cedar Creek levee May 16, 2019.
Minor damage to the levee crest due to high water overtopping the Cedar Creek levee May 16, 2019.
Pre-qualified contractors conduct a site visit at the Cedar Creek levee on Aug. 29, 2019 to view the scope of work on site in order to make an accurate bid.

Video Gallery

Video by Douglas Stutz
Naval Hospital Bremerton Patient Obstetric Navigator program
Naval Hospital Bremerton/Navy Medicine Readiness and Training Command Bremerton
June 8, 2023 | 3:59
For all of our valued expectant patients enrolled to Naval Hospital Bremerton, Congratulations!
Your OB/GYN team is here to provide a warm catch and a warm handoff of support and guidance for accessing all your prenatal needs.
With our Labor and Delivery still on divert status, here’s how we will continue to support you during your pregnancy with our Obstetric Patient Navigator program.

Who is eligible for the Obstetric Patient Navigator program?
We will provide support for all active-duty personnel as well as those enrolled in TRICARE

Prime Prenatal Visits – What expectant mothers can expect?
While some clinics may offer earlier first prenatal appointments, the first prenatal visit can usually be expected between 10-14 weeks of pregnancy.

What’s My First Step?
Once your pregnancy is confirmed, contact your primary care manager (PCM) team at our Family Medicine Clinic. Request a referral for your prenatal care.

What if there is difficulty getting a referral?
Call NHB OB/GYN for assistance, 360-475-4995

What if I need care before the 10-14 week time frame?
Should you require care prior to this visit, please contact your PCM team or NHB OB/GYN, 360-475-4995.

What if it’s difficult scheduling a monthly appointment with a community OB/GYN provider?
Your NHB OB/GYN team can help with your prenatal care until your community provider can see you. If you have any questions, please contact us at 360-475-4995.

What if I have questions and concerns before my initial prenatal visit?
For those who have questions or concerns regarding your pregnancy or health prior to your first visit with your prenatal care provider, call OBGYN at 360-475-4995; contact your PCM team directly using MHS GENESIS Patient Portal or call the TRICARE appointment line 1-800-404-4506 to schedule a visit to your PCM.

What if I don’t have a primary care manager?
For those who don’t have a PCM, or are new to the area, arrangements can be made by contacting TRICARE West at www.TRICARE-West.com or calling 1-844-866-9378.

Getting a referral takes how long:
Referrals for prenatal care can take three to five business days for processing.

What should I be doing when waiting on the prenatal care referral?
We advocate to set up your user account with Health Net Federal Services to personally manage and view your referrals as desired at www.TRICARE-West.com or by calling 1-844-866-9378.

What if I get a Referral but don’t hear from the provider?
If you have not received a call to book your appointment with community OB/GYN provider, contact their office directly. They should reach out to you after your referral is approved to book your appointment. The contact information for your provider’s office will be listed on your www.TRICARE-West.com account information page.

For non-urgent concerns and questions, you may also call the 24/7 TRICARE Nurse Advice Line at 1-800-874-2273.
More