Cedar Creek Omaha (F&W) Restoration Information

Background: The Cedar Creek (Omaha F&W) – Platte River Right Bank Levee System was damaged during the 2019 Flood Event, leading to the Project Sponsor submitting a Public Law (PL) 84-99 Rehabilitation Assistance request to the US Army Corps of Engineers – Omaha District.

Current Action: Close out the construction contract.

Restoration Activities:

 

Full Repair Contract 

Contractor

Midwest Construction from Nebraska City, NE

Contract Amount

$1,343,000

Contract Award

October 4, 2019

  Construction Start

Late October 2019

Completion

December 12, 2019

 

 

 

 

 

 

 

 

 

Status Updates:

10 January 2020 - Work on the Cedar Creek levee repair contract is complete.

18 December 2019 - Work on the Cedar Creek levee repair contract is complete with final inspection occurring on 12 December 2019. The team is currently working on closing out the contract.

06 December 2019 - The contractor is currently 97 percent complete with levee repair work. The pre-final inspection was conducted on 25 November 2019 with final inspection tentatively scheduled for the week of 09 December 2019.

22 November 2019 - The contractor is placing riprap and bedding materials at two of the three damage locations, seeding the third damage location and is expected to be substantially complete with repairs by the end of the month.

08 November 2019 - The contractor mobilized to the site on 30 October 2019 and has begun work on repairing the levee.

24 October 2019 - The pre-construction team meeting was held on 16 October 2019 with notice to proceed issued on the same day. The contractor is scheduled to mobilize to the site to begin repairs on 28 October 2019.

13 October 2019 - Pre-construction team meeting is scheduled for the week of 14 October 2019, at which time it is anticipated notice to proceed with repairs will be issued and the contractor can begin the repair work.

04 October 2019 – The levee repair contract was awarded to Midwest Construction of Nebraska City, NE in the amount of $1,343,000 on 04 October 2019. The repair is estimated to be complete in mid April 2020.

27 September 2019 – Funds to repair the Cedar Creek levee system have been received. The construction contract is scheduled to be awarded by 04 October 2019.

13 September 2019 – The bid opening occurred on 04 Sep 2019. It is anticipated that this project will be awarded within a few weeks, pending receipt of project funding from USACE HQ.

04 September 2019 – Correction. The bid opening was conducted on 04 Sep 2019 and the team is anticipating awarding the construction contract by mid-to-late September. 

29 August 2019 – A construction contract to repair the Cedar Creek levee system was advertised to pre-qualified contractors on 21 August 2019 with award anticipated around 04 September 2019.  The pre-qualified contractors conducted a site visit on 29 August 2019 to view the scope of work on site in order to make an accurate bid.

23 August 2019 – The team is on scheduled to be done with the E&D process late summer. The project was advertised to the pre-qualified Contractor Pool on 21 August 2019 with award anticipated around 04 September 2019.

05 August 2019 – Engineering and Design (E&D) work continues for rehabilitating the Cedar Creek levee system. The team is still anticipating to be done with the E&D process by late summer.

16 July 2019 – An initial site damage assessment and economic analysis has been completed.  From this initial assessment the USACE team has determined that there are damages to the levee system that are eligible for PL 84-99 Rehabilitation Assistance. Engineering and Design (E&D) work is on-going for rehabilitating the Cedar Creek Levee System.  The team is anticipating to be done with the E&D process for repairing the damage identified by the late-summer 2019.

NOAA River Level Observations & Forecasts

NOAA Water Gauge Levels

Cedar Creek Omaha (F&W) Levee Imagery

Final inspection of Cedar Creek levee repair, Dec. 12, 2019
USACE Engineering and Construction Team and the Local Levee Sponsor conducting the Plan In-Hand Review on the Cedar Creek Levee Aug. 7, 2019.
Erosion and scour along the riverside channel bank extending into the levee section at Cedar Creek levee May 16, 2019.
Minor damage to the levee crest due to high water overtopping the Cedar Creek levee May 16, 2019.
Pre-qualified contractors conduct a site visit at the Cedar Creek levee on Aug. 29, 2019 to view the scope of work on site in order to make an accurate bid.

Video Gallery

Video by Maj. Wayne Clyne
Former Oregon Military Leaders Share Insights at ORNGA Conference
Oregon National Guard Public Affairs Office
Feb. 22, 2025 | 45:40
Former Oregon Adjutant General Maj. Gen. Raymond F. Rees and his former Chief of Staff retired Col. Donald F. Bond addressed attendees at the Oregon National Guard Association state conference on February 22, 2025. The event was held at the Armed Forces Reserve Center (AFRC) at Camp Withycombe in Clackamas, Oregon. During their presentation, the distinguished speakers shared their experiences and insights, focusing on leadership challenges in military service, the importance of mentorship in military careers, and strategic career management and planning. Maj. Gen. Rees brought significant perspective from his extensive military career, which included serving as Adjutant General of Oregon, Director of the Army National Guard, Acting Chief of the National Guard Bureau, and Deputy Assistant Secretary of the Army for Training, Readiness and Mobilization from 2014 to 2019. During his tenure as Adjutant General, Maj. Gen. Rees oversaw the Oregon National Guard's preparedness for both state and federal missions. His responsibilities encompassed managing the Oregon National Guard, Oregon State Defense Force, Joint Force Headquarters, and the Office of Oregon Emergency Management. In this role, he ensured the state maintained a ready force of citizen soldiers and airmen, equipped and trained to respond to any contingency, whether natural or man-made. The Oregon National Guard Association, which hosted the event, continues its vital mission as a professional organization dedicated to supporting the National Guard's constitutional roles through legislative, congressional, and executive advocacy. The speaking engagement provided current Guard members and attendees with valuable insights from these experienced leaders, drawing from their years of service and leadership in the Oregon National Guard. Their shared experiences and wisdom offered valuable guidance for those currently serving and highlighted the enduring importance of strong military leadership and mentorship in today's National Guard. (U.S. Army National Guard video by Maj. W. Chris Clyne, Oregon National Guard Public Affairs)
More