Cedar Creek Omaha (F&W) Restoration Information

Background: The Cedar Creek (Omaha F&W) – Platte River Right Bank Levee System was damaged during the 2019 Flood Event, leading to the Project Sponsor submitting a Public Law (PL) 84-99 Rehabilitation Assistance request to the US Army Corps of Engineers – Omaha District.

Current Action: Close out the construction contract.

Restoration Activities:

 

Full Repair Contract 

Contractor

Midwest Construction from Nebraska City, NE

Contract Amount

$1,343,000

Contract Award

October 4, 2019

  Construction Start

Late October 2019

Completion

December 12, 2019

 

 

 

 

 

 

 

 

 

Status Updates:

10 January 2020 - Work on the Cedar Creek levee repair contract is complete.

18 December 2019 - Work on the Cedar Creek levee repair contract is complete with final inspection occurring on 12 December 2019. The team is currently working on closing out the contract.

06 December 2019 - The contractor is currently 97 percent complete with levee repair work. The pre-final inspection was conducted on 25 November 2019 with final inspection tentatively scheduled for the week of 09 December 2019.

22 November 2019 - The contractor is placing riprap and bedding materials at two of the three damage locations, seeding the third damage location and is expected to be substantially complete with repairs by the end of the month.

08 November 2019 - The contractor mobilized to the site on 30 October 2019 and has begun work on repairing the levee.

24 October 2019 - The pre-construction team meeting was held on 16 October 2019 with notice to proceed issued on the same day. The contractor is scheduled to mobilize to the site to begin repairs on 28 October 2019.

13 October 2019 - Pre-construction team meeting is scheduled for the week of 14 October 2019, at which time it is anticipated notice to proceed with repairs will be issued and the contractor can begin the repair work.

04 October 2019 – The levee repair contract was awarded to Midwest Construction of Nebraska City, NE in the amount of $1,343,000 on 04 October 2019. The repair is estimated to be complete in mid April 2020.

27 September 2019 – Funds to repair the Cedar Creek levee system have been received. The construction contract is scheduled to be awarded by 04 October 2019.

13 September 2019 – The bid opening occurred on 04 Sep 2019. It is anticipated that this project will be awarded within a few weeks, pending receipt of project funding from USACE HQ.

04 September 2019 – Correction. The bid opening was conducted on 04 Sep 2019 and the team is anticipating awarding the construction contract by mid-to-late September. 

29 August 2019 – A construction contract to repair the Cedar Creek levee system was advertised to pre-qualified contractors on 21 August 2019 with award anticipated around 04 September 2019.  The pre-qualified contractors conducted a site visit on 29 August 2019 to view the scope of work on site in order to make an accurate bid.

23 August 2019 – The team is on scheduled to be done with the E&D process late summer. The project was advertised to the pre-qualified Contractor Pool on 21 August 2019 with award anticipated around 04 September 2019.

05 August 2019 – Engineering and Design (E&D) work continues for rehabilitating the Cedar Creek levee system. The team is still anticipating to be done with the E&D process by late summer.

16 July 2019 – An initial site damage assessment and economic analysis has been completed.  From this initial assessment the USACE team has determined that there are damages to the levee system that are eligible for PL 84-99 Rehabilitation Assistance. Engineering and Design (E&D) work is on-going for rehabilitating the Cedar Creek Levee System.  The team is anticipating to be done with the E&D process for repairing the damage identified by the late-summer 2019.

NOAA River Level Observations & Forecasts

NOAA Water Gauge Levels

Cedar Creek Omaha (F&W) Levee Imagery

Final inspection of Cedar Creek levee repair, Dec. 12, 2019
USACE Engineering and Construction Team and the Local Levee Sponsor conducting the Plan In-Hand Review on the Cedar Creek Levee Aug. 7, 2019.
Erosion and scour along the riverside channel bank extending into the levee section at Cedar Creek levee May 16, 2019.
Minor damage to the levee crest due to high water overtopping the Cedar Creek levee May 16, 2019.
Pre-qualified contractors conduct a site visit at the Cedar Creek levee on Aug. 29, 2019 to view the scope of work on site in order to make an accurate bid.

Video Gallery

Video by Courtesy
25 [3/3] - John J. Hammerer – The World of Combat Systems
Naval Postgraduate School
April 23, 2021 | 21:23
25 [3/3] - John J. Hammerer - The World of Combat Systems
The Trident Room Podcast host Marcus Antonellis sits down with John J Hammerer – they discuss the real-world challenges of air and missile defense and the initiation of The Meyer Scholar Program.
This episode was recorded on April 23, 2021.

John Hammerer is the Chair, Integrated Air and Missile Defense at the U.S. Naval Postgraduate School. Previously he served as a Senior Research Scientist at the Center for Naval Analyses, the Navy’s Federally Funded Research and Development Center where his principal areas of research included combat systems development and operational warfighting assessment.

Prior to joining the Center for Naval Analyses, he was a defense consultant to the AEGIS and New Construction Ships Branch in the Office of the Chief of Naval Operations and the AEGIS Ballistic Missile Defense Program Office. In this capacity he was a member of several study groups including the Congressionally mandated BMDS Training and Education Needs Assessment and the DDG-1000 Combat System Activation Readiness Assessment.

John’s eight shipboard assignments, included duty as the commissioning Commanding Officer of USS Paul Hamilton and command of USS Lake Erie, conducting the first ballistic missile intercepts in space from a ship at sea.

Ashore, he served as the Commander of the Ballistic Missile Defense Organization’s Joint National Test Facility, the Director of the Missile Defense Agency’s Initial Defensive Operations Task Force and Program Manager of the Ground Based Midcourse Defense Fire Control and Communications System. He also led the Ballistic Missile Defense Organization’s Joint Force and Test and Evaluation of Battle Management Command, Control, and Communications, and Intelligence Directorate. John was the Surface and Strike Warfare Officer in Combat System Engineering Branch of the AEGIS Program Office’s Technical Division.

Prior to reporting to the Naval Postgraduate School, he was an adjunct professor of Joint Maritime Operations at the U.S. Naval War College.

He holds a Bachelor of Science degree in Marine Science from the University of South Carolina, a Master of Science degree in Physics from the U.S Naval Postgraduate School and a Master of Arts degree in National Security and Strategic Studies from the U.S. Naval War College. He was certified as a Joint Specialty Officer and Acquisition Professional Level III in Program Management.

The Trident Room Podcast is brought to you by the Naval Postgraduate School Alumni Association and the Naval Postgraduate School Foundation.
npsfoundation.org

For comments, suggestions, and critiques, please email us at TridentRoomPodcastHost@nps.edu, and find us online at nps.edu/tridentroompodcast. Thank you!
More