|
Regional Watershed
Supply Project
Environmental Impact Statement (RWSP EIS)
Aaron Million:
Proposed Water Supply Pipeline
From Flaming Gorge Reservoir in Wyoming to Colorado
The Corps terminated the RWSP EIS
on July 14, 2011.
For related information, please refer to the public notice
found
here.
All information below, displayed on this page
before the study
was terminated, will remain available
until July 14, 2012 for historical reference and context.
Introduction
The US
Army Corps of Engineers, Omaha District, (Corps) is preparing an Environmental Impact Statement (EIS) to
evaluate the environmental consequences of the proposed Regional
Watershed Supply Project (RWSP).
The
RWSP is proposed by Million
Conservation Resource Group (MCRG), a private water development
entity. MCRG proposes to withdraw approximately 250,000 acre-feet
(AF) of water annually from the Green River and Flaming Gorge Reservoir in
Wyoming,
and transport it by pipeline to
existing and proposed new reservoirs in southeastern Wyoming and the
Front Range of Colorado.
What is an
Environmental Impact Statement (EIS)?
An environmental impact
statement (EIS) is a document required by the National Environmental
Policy Act (NEPA) for federal government agency actions "significantly
affecting the quality of the human environment."
Although the Corps is not proposing,
designing, funding or constructing the RWSP, the RWSP will require a
Section 404 Permit, which is a federal permit required under
the Clean Water Act administered by the Corps. Because a Section
404 Permit is required, the Corps is the lead federal agency managing the EIS process.
The NEPA process is designed to involve
the public and gather the best available information regarding the
project so decision makers can be fully informed when they make their
choices. An EIS describes the positive and negative environmental
effects of proposed agency action - and cites alternative actions.
The components of the EIS
process are public involvement, scoping, preparation of a Draft EIS, and
preparation of a Final EIS and Record of Decision.
The Draft EIS is estimated to be released in 2016 and
the Final EIS in 2018.
(top of page)
US Army Corps of
Engineers Involvement with the EIS
The Corps, through requirements contained
in Section 404 of the Clean Water Act, regulates activities involving
the discharge of dredged or fill material into waters of the U.S. Any
individual or agency, public or private, must receive authorization from
the Corps before conducting such discharges, and documentation of
compliance with the National Environmental Policy Act (NEPA) must occur
before a permit may be issued. For projects where the potential impacts
to the environment are significant, an EIS is required.
Under Section 404, any person has the right, at any
point in time, to apply for a permit. The Corps role in this process is to develop a thorough study that can guide the agency in making an
informed decision about whether to approve or deny the permit. The Corps
is neither an opponent nor a proponent of any project that must undergo
the permit process.
In the case of the RWSP,
many have questioned why the Corps began the EIS process without having
definitively determined the amount of water available for use in
Colorado under the Colorado River Compacts, or without definitively
knowing who would use the water.
After working with MCRG, as well as coordinating with
the Bureau of Reclamation and Bureau of Land Management, for more than
one and a half years, the Corps determined that the project requires an
EIS, and that now is the correct time to begin the NEPA process.
Preparation of the EIS is being funded by MCRG, through payment of a
third-party contractor who is under the direct supervision of the Corps.
In defining a project purpose, the Corps must comply with NEPA. The
project purpose is commonly referred to as the purpose and needs
statement. The NEPA process gives the public the opportunity to comment
on the proposed projects impacts, potential mitigation measures and the
potential alternatives to be analyzed during the development of the EIS.
The Corps reviews and considers public comments when developing the
purpose and needs statement. The Corps then uses that statement to
evaluate alternatives, and independently verify the projects need.
Critical questions, such as how much water is available and who will use
the water, will be answered through the NEPA process. Those questions
must be answered before the Corps determines whether to approve or deny
the permit.
MCRG submits
water user information to Corps 20-Jan-10
Corps
requests additional info from MCRG 31-Jul-09
Why the Corps is preparing an EIS 14-Apr-09
(top of page)
Cooperating Agencies
US Bureau of Reclamation.
US Forest Service Ashley National Forest.
US Environmental Protection Agency.
National Park Service.
State of Colorado Department of Natural Resources.
State of Wyoming Wyoming Water Development Office.
State of Utah Public Lands Policy Coordination Office.
Moffat County, Colorado.
Daggett County, Utah.
Uintah County, Utah.
Sweetwater County, Wyoming.
Sweetwater County Conservation District, Wyoming.
City of Green River, Wyoming.
City of Rock Springs, Wyoming.
(top of page)
Project Description
The proposed RWSP would make new water
supply available for use by municipalities, agriculture, and industries
in southeastern Wyoming and the Front Range of
Colorado.
Withdrawal Facilities - Two water
withdrawal facilities would be used, one on east side of
Flaming Gorge
Reservoir in Wyoming and the other on the east bank of the Green River
in Wyoming approximately 200 feet downstream
of the
Seedskadee National Wildlife Refuge in Wyoming. The total right-of-way
(ROW) width would be 200 feet (100 feet construction and 100 feet
permanent).
Withdrawal Volumes - The total
estimated
annual volumes
from the two diversion points are approximately 165,000 AF from Flaming
Gorge Reservoir and 85,000 AF from the Green River during a dry year.
The Green River volumes would increase to approximately 157,000 AF in an
average year and 195,000 AF in a wet year. These withdrawal rates are
estimates based upon historical streamflow conditions during the 1971 to
2007 period of record; therefore, the future effects of increased
depletions in Wyoming upstream of the withdrawal facilities have not
been considered at this time.
Pipeline System - Water pipeline system (approximately 578
miles in length with diameters of 72 to 120 inches) would extend from
the withdrawal points to southeastern Wyoming and the Front Range of
Colorado
between the Wyoming-Colorado state line and
Pueblo.
Pump Stations - Approximately 16
natural gas-powered pump stations would be located along the pipeline
route. The total ROW width would be 20 acres (10 acres construction and
10 acres permanent). (Pump
Station Details)
Valves - Three types of
appurtenance valves
(air
release/vacuum, isolation, and drain)
would be
located along the pipeline route. All valves would be located within the
permanent ROW.
Access Roads -Temporary
(construction
phase) and
permanent (operation and maintenance phase) access roads would
be required.
Specific roads will be identified during project design.
Water Storage - Three water
storage reservoirs (Lake Hattie (69,000 AF capacity) in Wyoming,
proposed Cactus Hill Reservoir (185,000 AF capacity) near Fort Collins,
Colorado, and new reservoir (25,000 AF
capacity) to
be constructed near Pueblo, Colorado would be utilized as storage
reservoirs.
Electrical Power - On-site
transformers and
overhead power
lines from local electrical grids would be used as power sources for the
water withdrawal and storage reservoir
facilities.
Water Delivery Systems Specific
water
users and water
delivery systems from the storage reservoirs
will be determined.
(top of page)
Maps and Diagrams
Overall Project Location Map
(MCRG's preferred pipeline route)
Overview of Alternative Diversion Points
& Pipeline Routes near Flaming Gorge Reservoir
Alternative Diversions
Flaming Gorge Reservoir East Bank Diversion
Flaming Gorge Reservoir West Bank Diversion
Green River Diversion
Seedskadee Diversion
Alternative Reservoirs
West End Retention Reservoir
(Near Green River, WY)
Lake Hattie Reservoir
(Near Laramie, WY)
Proposed Cactus Hill Reservoir
(Near Fort Collins, CO)
Proposed T-Cross Reservoir
(Near Pueblo, CO)
(top of page)
Public Scoping
What is public scoping?
Public Scoping is a process that allows for public participation with
regard to identifying concerns and issues related to the preparation of
and Environmental Impact Statement (EIS). At the beginning of the RWSP
EIS process, the Corps conducted scoping meetings to introduce the
project proposal to the public, describe the process of the EIS, and
solicit input on the issues and alternatives to be evaluated. The
received comments were then summarized in a scoping report.
Past Scoping Meetings
April 14, 2009, Green
River, WY
April 15, 2009, Vernal, UT
April 16, 2009, Laramie, WY
April 20, 2009, Fort Collins, CO
April 21, 2009, Denver, CO
April 22, 2009, Pueblo, CO
June 9, 2009, Rock Springs, WY
June 10, 2009, Craig, CO
June 11, 2009, Grand Junction, CO
Public Scoping
Brochure June 2009
Public Scoping
Meeting Posters and Maps
RWSP EIS Public Scoping Summary Report
RWSP EIS Scoping Summary Report (Posted 16-Feb-10, 110 pgs, 9MB)
Scoping
Comments Received - Federal (Posted 16-Feb-10, 45pgs, 587 KB)
Scoping Comments Received Tribal
Organizations (Posted 16-Feb-10, 3 pgs, 264 KB)
Scoping Comments Received State and
Regional (Posted 16-Feb-10, 45 pgs, 590 KB)
Scoping Comments Received
Counties (Posted 16-Feb-10, 172 pgs, 2 MB
Scoping Comments Received Municipalities
(Posted 16-Feb-10, 12 pgs, 634 KB)
Scoping Comments Received Water,
Conservation, and Special Districts (Posted 16-Feb-10, 35 pgs, 1 MB)
Scoping Comments Received Organizations
(Posted 16-Feb-10, 363 pgs, 6 MB)
Scoping Comments Received Citizen
Letters (Posted 16-Feb-10, 267 pgs, 16 MB)
Scoping
Comments Received Citizen E-mails (Posted 16-Feb-10, 299 pgs, 5MB)
Scoping Comments Received Citizen Comment Forms (Posted 16-Feb-10, 394
pgs, 19 MB)
Scoping
Comments Received Public Meeting Notes (Posted 16-Feb-10, 124 pgs, 17
MB)
(top of page)
Public Notices
Public Notice #3 - Comment
Period Extension to Sept 28, 2009 11-Aug-09
Federal Register Notice of Intent
11-Aug-09
Public Notice
#2 - Comment Period Extension to July 27, 2009 add'l Public Scoping Mtgs
8-May-09
Federal Register Notice of Intent
8-May-09
Public Notice #1 - Comment
Period and Public Scoping Mtgs 20-Mar-09
Federal Register Notice of Intent 20-Mar-09
(top of page)
For Further EIS Information on the RWSP, Contact:
Rena J. Brand (303) 979-4120 or Monique
Farmer (402) 995-2417 or Toll Free 1-888-835-5971
Or send an E-Mail to:
MCRG.EIS@usace.army.mil
|