Home
Home > Missions > Regulatory Program > Nebraska > Public Notices

Public Notices

1 2 3


NWO-2010-02760-WEH_2 - 2/12/2018: Thomas Dredging & Excavating - An after-the-fact standard permit was authorized for this project on August 27, 2012. That permit expired on August 31, 2017. The project was not completed and the applicant allowed the permit to expire without requesting an extension of time to complete the permitted activity. The applicant is requesting a new authorization to complete the residential lakeside development that was originally authorized. The proposed project consists of the construction of a residential lakeside development, surrounding a completed sand and gravel mine. The waste sand from the adjacent sand and gravel mining operation will be placed into Lake Allure to allow for residential development. The project includes construction of 144 lakeside residential lots. Lots 58 through 96 and lots 137 to 144 are not completed as shown on the drawings, as well as open spaces, pathways, roadways, road improvements, water lines, sanitary sewer lines, utility lines, and water and sewer storage facilities. The original project impacted 2,250 linear feet of an unnamed tributary to the Platte River via excavation by sand and gravel mining. The unnamed tributary was relocated as compensatory mitigation. The channel relocation is complete, but not all of the required channel monitoring has been completed. The applicant will be required to complete the channel monitoring. Thirty acres of the 200-acre Lake Allure were proposed to be filled to accommodate the residential development under the original permit. There are 18 acres of Lake Allure yet to be filled.
Expiration date: 2/5/2018

ATTACHMENTS:  


NWO-2014-01511-WEH - 2/2/2018: Office of Douglas County Engineer - The proposed Douglas County Mitigation Bank Site is located in W ½ of Section 10, Township 16 North, Range 11 East in Douglas County, Nebraska. The project purpose is to develop certified wetland and stream mitigation credits for allocation toward unavoidable resource impacts resulting from future/undetermined Douglas County public works projects as well as accepting funds from other entities in exchange for bank credits.
Expiration date: 2/1/2018

ATTACHMENTS:  


NWO-2016-00132-WEH - 1/25/2018: Nebraska Department of Transportation - The NDOT is proposing to improve 6.46 miles of N-96 near the City of Burwell, Nebraska. The work on highway N-96 would require completion of two segments to two different design standards. One segment would be built to 3R (Resurfacing, Restoration, and Rehabilitation) standards and the other segment would be built to DR-5 (New and Reconstruction) standards. The 3R portion of this project consists of the entire roadway within the described project areas, except for two segments associated with the Calamus River and North Loup River, where off-alignment construction would occur. The 3R portion of this project would upgrade the existing roadway on this segment of N-96 with two 11-foot wide asphalt lanes and 3-foot wide earth shoulders. The improvements on this project are comprised of pavement widening, asphalt repairs, milling and resurfacing resulting in a 28-foot surfaced top, reconstruction of existing surfaced drives and intersections, replacement of existing culverts, and construction of new culverts. The DR-5 portions of this project would construct two new bridges on N-96 to replace the bridges currently crossing the Calamus River and the North Loup River. Highway approaches to these structures would be built to DR-5 standards. Additional improvements would include grading work, construction of new horizontal and vertical alignments, reconstructing the adjacent roadway and shoulders, removal of the existing bridges, installation of new guardrail, surfacing under guardrail and earth shoulder construction, all of which would be determined by Roadway Design.
Expiration date: 2/14/2018

ATTACHMENTS:  


1 2 3