Home
Stop Aquatic Hitchhikers! Prevent invasive species Water Safety Reserve a campsite at USACE campgrounds at Recreation.gov Purchase Navigation and Boating Maps from the Jefferson National Parks Association
Collapse All Expand All

Oahe Dam’s layout is unique in that the power house is on the left bank, the outlet works on the right bank, and the spillway is one mile beyond the outlet works.

The first of the power house’s seven 89,500-kilovolt generators was put into operation in March 1962.  On August 17, 1962, President John F. Kennedy came to the dam and officially dedicated the two generators.  The final generator went into operation in June 1963, completing the $340-million Oahe project.  By 1966, Oahe Dam was generating over 2 billion kilowatt-hours of electricity annually.

Oahe generators provide enough electricity to meet the annual needs of 259,000 homes. 

Characteristics and Value

Generators/Turbines

7 Francis Turbines, 100 rpm

Nameplate Capacity

786 MW/112.3 MW each

Percent of NWO Capacity

31.43%

Average Gross Head Available

174 ft

Number & size of conduits

7-24’ dia, imbedded penstocks

Surge Tanks

70’ dia, 2 per penstock

Discharge Capacity

185 feet at 54,000 cfs

Average Annual Energy

2,641 M kWh

Hydropower Master Plan

The Omaha District has prepared a Hydropower Master Plan outlining the future requirements for sustaining our hydropower mission capability. A strategic master plan will guide future programming and funding for all hydropower sustainment, rehabilitation, and modernization requirements in a way that provides predictable funding and maximizes efficiencies to ensure the long-term resilience and reliability of this critical national infrastructure.

Hydropower Master Plan Book Cover